CITB Heating and Plumbing Services: Core: working environment and legal duties practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

16 of our 200 CITB HS&E Specialist Test: Heating and Plumbing Services (CITB-SPEC-HAPS) questions are on core: working environment and legal duties, about 8% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. What must a site rest area have for the people likely to use it?

Show answer

Answer: A. Enough tables and seating with backs

  • Rest rooms or areas must have an adequate number of tables and seating with backs.
  • Where needed, there must be somewhere for a pregnant worker or nursing mother to lie down.

They must be readily accessible.

Why the others are wrong:

B: lockers relate to changing facilities, not rest areas.

C: first aid is a separate duty and not part of the rest area rule.

D: these may be nice to have but are not required.

Memory trick:

Back to the bench: seats need backs.

Find it in the book

HSE L153 (2015), page 64

Reg HSE L153 (2015), Schedule 2, paragraph 5(2)

Q2. A lorry-mounted crane delivering a chiller touches an overhead power line. Nobody is hurt. What is this under RIDDOR?

Show answer

Answer: C. A reportable dangerous occurrence

  • Dangerous occurrences are specified near misses that must be reported.
  • Examples include plant contacting overhead power lines and collapse of lifting equipment.

No injury is needed for it to be reportable.

Why the others are wrong:

A: the dutyholder in control of the work must report it.

B: damage is not the test; the contact itself is reportable.

D: plant contacting overhead lines is a listed dangerous occurrence.

Memory trick:

Touch a line, report the time.

Find it in the book

HSE INDG453 (rev1, 2013), page 3

Reg HSE INDG453 (rev1, 2013), reportable dangerous occurrences

Q3. You notice a guard rail missing on a plant room mezzanine. What does the law say you must do?

Show answer

Answer: A. Report the hazard to your employer

  • Employees must report any safety hazard they identify to their employer.
  • They must use equipment and safety devices properly, following training.

Employees also have a general duty to co-operate with their employer.

Why the others are wrong:

B: your employer must be told so it can be dealt with.

C: employees have a legal duty to report hazards.

D: makeshift repairs can create new risks; report it.

Memory trick:

See it, say it.

Find it in the book

HSE INDG401 (rev2, 2014), page 6

Reg HSE INDG401 (rev2, 2014), what must employees do

Q4. On a heating and plumbing job, where must the site washing facilities be provided?

Show answer

Answer: A. In the immediate vicinity of every toilet

  • Washing facilities must be in the immediate vicinity of every sanitary convenience.
  • They are also needed near any changing rooms.

This is part of the minimum welfare in CDM Schedule 2.

Why the others are wrong:

B: no such distance is set; they must be next to every sanitary convenience.

C: washing facilities must be next to the toilets, whether or not provided elsewhere.

D: washing facilities are a basic requirement on every site.

Memory trick:

Flush then wash, side by side.

Find it in the book

HSE L153 (2015), page 63

Reg HSE L153 (2015), Schedule 2, paragraph 2(2)

Q5. A client takes on two specialist firms, one for pipework and one for controls, on the same job. What must the client do?

Show answer

Answer: A. Appoint a principal designer and principal contractor

  • Where there is, or will be, more than one contractor, the client must appoint a principal designer and a principal contractor.
  • The appointments must be in writing.

If the client fails to appoint, the client takes on those duties.

Why the others are wrong:

B: the appointment must be made by the client, in writing.

C: insurance does not replace the CDM duty to make appointments.

D: HSE does not appoint dutyholders on a project.

Memory trick:

Two contractors, two appointments.

Find it in the book

HSE L153 (2015), page 15

Reg HSE L153 (2015), regulation 5(1)

Q6. A plant room refit is planned to last 45 working days, with never more than 12 workers on site at once. Is it notifiable to HSE?

Show answer

Answer: C. Yes, because it will exceed 500 person days

  • A project is notifiable if it lasts more than 30 working days with more than 20 workers at once, or exceeds 500 person days.
  • 45 days x 12 workers = 540 person days, so it is notifiable.

The client sends the notice to HSE before the construction phase starts.

Why the others are wrong:

A: over 30 days it also needs more than 20 workers at once; here it is the person days that trigger it.

B: 60 working days is not a CDM test; the figures are 30 working days or 500 person days.

D: the 20-worker test is only one route; the job still exceeds 500 person days.

The maths

45 working days x 12 workers = 540 person days
540 is more than 500, so the project is notifiable

Memory trick:

30 days and 20 people, or 500 person days.

Find it in the book

HSE L153 (2015), page 20

Reg HSE L153 (2015), regulation 6(1)

Want 194 more CITB Heating and Plumbing Services questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other CITB Heating and Plumbing Services topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (HSE, GOV.UK). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic