CITB Heating and Plumbing Services: Core: occupational health practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

16 of our 200 CITB HS&E Specialist Test: Heating and Plumbing Services (CITB-SPEC-HAPS) questions are on core: occupational health, about 8% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. How often must local exhaust ventilation have a thorough examination and test?

Show answer

Answer: A. At least once every 14 months

  • LEV needs thorough examination and testing at least every 14 months.
  • More often for processes in Schedule 4 of COSHH.

Keep records of checks for at least five years.

Why the others are wrong:

B: LEV needs regular thorough examination, not just at start.

C: this is far too long for LEV.

D: 6 months applies to some lifting equipment, not LEV.

Memory trick:

LEV: fourteen months max.

Find it in the book

HSE INDG136 (rev5, 2012), page 6

Reg HSE INDG136 (rev5, 2012), local exhaust ventilation

Q2. At what daily noise exposure must an employer provide hearing protection and make sure it is worn?

Show answer

Answer: D. 85 dB(A)

  • Lower exposure action value: 80 dB. Upper exposure action value: 85 dB.
  • Above the upper value, hearing protection must be provided and used.

The exposure limit of 87 dB allows for the protection worn.

Why the others are wrong:

A: 80 dB is the lower action value, where protectors are given on request.

B: 87 dB is the exposure limit, not the action value.

C: 90 dB is not an action value in the current regulations.

Memory trick:

80 ask, 85 must, 87 never.

Find it in the book

HSE INDG362 (rev2, 2012), page 4

Reg HSE INDG362 (rev2, 2012), exposure action values

Q3. Under COSHH, which control should you consider first?

Show answer

Answer: B. Use a safer product instead

  • First: eliminate the harmful substance or use a safer one.
  • PPE is the last resort, after enclosure, extraction and limiting numbers.

Controls should be used together where several are needed.

Why the others are wrong:

A: extraction comes after removing or substituting the substance.

C: PPE is the last option on the list.

D: limiting numbers comes after substitution and engineering controls.

Memory trick:

Swap it before you mask it.

Find it in the book

HSE INDG136 (rev5, 2012), page 5

Reg HSE INDG136 (rev5, 2012), choosing control measures

Q4. Which sign suggests noise in a plant room needs assessing?

Show answer

Answer: B. You must raise your voice to talk 2 m apart

  • If people have to raise their voices for a normal conversation about 2 m apart, noise needs looking at.
  • Using noisy powered tools for more than half an hour a day is another sign.

A risk assessment then decides the action needed.

Why the others are wrong:

A: normal conversation at close range suggests noise is not a problem.

C: a hum is not in itself a sign of harmful noise.

D: hearing plant from outside is not the rule of thumb.

Memory trick:

Shout at two metres, assess it.

Find it in the book

HSE INDG362 (rev2, 2012), page 2

Reg HSE INDG362 (rev2, 2012), do I have a noise problem

Q5. What is the daily noise exposure limit, and how is it measured?

Show answer

Answer: A. 87 dB, allowing for the hearing protection worn

  • Daily or weekly exposure must not exceed 87 dB, after allowing for hearing protection.
  • The peak sound pressure limit is 140 dB.

Action values are worked out without any allowance for protectors.

Why the others are wrong:

B: 140 dB is the peak sound pressure limit, not the daily one.

C: 85 dB is the upper action value and ignores protectors.

D: the limit is the only value that takes protectors into account.

Memory trick:

Limit counts the plugs.

Find it in the book

HSE INDG362 (rev2, 2012), page 6

Reg HSE INDG362 (rev2, 2012), exposure limits

Q6. What is the daily exposure limit value for hand-arm vibration?

Show answer

Answer: B. 5 m/s² A(8)

  • Exposure action value (EAV): 2.5 m/s² A(8).
  • Exposure limit value (ELV): 5 m/s² A(8), which must not be exceeded.

Above the EAV, exposure must be reduced as low as reasonably practicable.

Why the others are wrong:

A: 2.5 is the exposure action value, not the limit.

C: 1.5 is not a value set in the regulations.

D: 10 is not a value set in the regulations.

Memory trick:

Act at 2.5, stop at 5.

Find it in the book

HSE INDG175 (rev3, 2012), page 2

Reg HSE INDG175 (rev3, 2012), what the law says

Want 194 more CITB Heating and Plumbing Services questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other CITB Heating and Plumbing Services topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (HSE, GOV.UK). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.