AM2S v1 Knowledge Test: Health and safety practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

28 of our 180 AM2S v1 Knowledge Test (Section E) (AM2S-V1) questions are on health and safety, about 16% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. You are working under an electrical permit-to-work and find the job needs an extra cable pulled into a different panel not named on the permit. What should happen?

Show answer

Answer: C. Cancel the permit and get a new one from its issuer before the work changes

  • HSG85: if the programme of work must change, the existing permit-to-work should be cancelled and a new one issued before any variation.
  • Only the person who issued the original permit, or the person nominated to take over, can agree the change and issue the new permit.
  • Nobody should work on equipment that the permit does not list as made safe.

A permit is a precise record of what has been made safe, so it cannot be stretched.

Why the others are wrong:

A: nobody may work on equipment not specified on the permit as made safe; a change needs a new permit.

B: verbal assurance is not a permit; the existing permit must be cancelled and a new one issued.

D: the permit system controls what has been made safe; work outside it is not allowed until a new permit is issued.

Memory trick:

New job, new permit.

Find it in the book

HSE HSG85 (3rd edition), page 24

Reg HSG85, paragraph 72

Q2. You are stripping out old circuits in a shop that are being abandoned. What does HSR25 say you must do before the equipment is dismantled?

Show answer

Answer: D. Disconnect it from every supply source and secure it against re-energising

  • HSR25: before equipment is decommissioned, dismantled or abandoned, it must be disconnected from all sources of supply.
  • Effective steps must be taken so it is dead and cannot inadvertently become re-energised; securely marking or labelling may be needed.

Abandoned live cables are a common cause of shocks to the next trade on site.

Why the others are wrong:

A: switching off is not enough; abandoned equipment must be disconnected from every source and secured.

B: fuses can be replaced; HSR25 requires disconnection from all sources and steps so it cannot be re-energised.

C: the equipment must be disconnected at its supply first; cutting at the work point risks cutting a live cable.

Memory trick:

Abandoned means disconnected, not just off.

Find it in the book

HSE HSR25 (3rd edition), page 37

Reg HSR25, paragraph 199

Q3. You need to run a cable across a pitched slate roof to a new PV array. How should you treat the slates?

Show answer

Answer: A. As likely to be fragile, not able to take your weight

  • INDG401 lists surfaces likely to be fragile, including roof lights, non-reinforced fibre cement sheets, corroded metal sheets and slates and tiles.
  • Falls through fragile roofs are one of the most common causes of workplace death and serious injury.

Plan access with the right equipment, such as a roof ladder or scaffold.

Why the others are wrong:

B: HSE lists slates and tiles among surfaces likely to be fragile.

C: fragility is about whether the material can bear a load, not the pitch.

D: HSE lists slates and tiles generally as likely to be fragile, not only damaged ones.

Memory trick:

Slates and tiles: treat as fragile.

Find it in the book

HSE INDG401 (rev2), page 3

Reg INDG401, What are the most common causes of accidents when working at height?

Q4. Your firm is the only contractor rewiring a shop. Who must make sure a construction phase plan is prepared before work starts?

Show answer

Answer: C. Your firm, as the contractor on a single-contractor project

  • A construction phase plan sets out the health and safety arrangements and site rules, and must be prepared before the construction phase begins.
  • For single-contractor projects, the contractor must ensure the plan is prepared; with more than one contractor, it is the principal contractor's duty.

The plan can be short and proportionate for a small job.

Why the others are wrong:

A: building control has no duty under CDM 2015 to prepare the construction phase plan.

B: a principal designer is appointed where there is more than one contractor; the contractor prepares the plan here.

D: CDM 2015 requires a construction phase plan for every project; on a single-contractor job the contractor makes sure it is done.

Memory trick:

One contractor, one plan, your plan.

Find it in the book

HSE L153 (2015), page 19

Reg L153, paragraph on the construction phase plan

Q5. You lift a drum of cable from the floor up onto a bench, so your hands pass through more than one zone of HSE's lifting filter. Which filter value should you use?

Show answer

Answer: B. The smallest weight of the zones your hands pass through

  • INDG143: decide which zone or zones the hands pass through and compare the weight with the filter value.
  • If the hands enter more than one zone, use the smallest weight. Use an in-between value only if the hands are close to a boundary.

The filter values are not 'safe limits'; they help pick out low-risk tasks.

Why the others are wrong:

A: the start and finish zones are not chosen alone; the smallest value applies.

C: HSE says to use the smallest weight when the hands enter more than one zone.

D: HSE uses an in-between value only when the hands are close to a zone boundary; otherwise use the smallest.

Memory trick:

Several zones? Take the smallest.

Find it in the book

HSE INDG143 (rev4), page 7

Reg INDG143, Lifting and lowering risk filter

Q6. The board schedule says way 4 is the kitchen sockets. You switch off and lock way 4. What should you do before touching the kitchen socket terminals?

Show answer

Answer: A. Prove the socket conductors dead, as labels can't be trusted

  • HSG85: correct labelling is important, but it should never be assumed that labelling is correct.
  • Work must not start until the circuit or equipment has been proved dead at the point of work.

Boards are often relabelled badly over the years, so the test is what protects you.

Why the others are wrong:

B: HSG85 says it should never be assumed that labelling is correct; the circuit must be proved dead first.

C: a lamp going out does not prove every conductor dead; use an approved voltage indicator and prove it before and after.

D: the customer's check is not proving dead; you must test at the point of work yourself.

Memory trick:

Trust the tester, not the label.

Find it in the book

HSE HSG85 (3rd edition), page 21

Reg HSG85, paragraph 47

Want 174 more AM2S v1 Knowledge Test questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other AM2S v1 Knowledge Test topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (HSE). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic