The inspection and testing sequence, test by test
Updated 15 October 2026. Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).
BS 7671 Part 6 sets out the tests for a new installation in an order that matters. The dead tests come first, so you know the installation is safe to energise. Only then do you switch on and do the live tests.
Here is the full sequence, what each test proves, and links to a guide on each one. It is the backbone of the 2391-50, 2391-51 and 2391-52 exams.
Before you test: inspection
Inspection comes before testing and is done with the installation isolated. You check the right equipment has been selected and installed correctly, against the schedule of inspections: cable routes and safe zones, connections, labels, protective devices, bonding, IP ratings and so on. Many faults are found by looking before anything is tested.
Dead tests, in order
| Test | What it proves |
|---|---|
| 1. Continuity of protective conductors | Every CPC and bonding conductor is connected end to end, with a low resistance |
| 2. Continuity of ring final circuit conductors | Each ring is a complete loop with no breaks or interconnections |
| 3. Insulation resistance | No short circuits between live conductors, or between live conductors and earth |
| 4. Protection by SELV, PELV or electrical separation | The separation from other circuits is intact, where these measures are used |
| 5. Polarity | Switches and single-pole devices are in the line conductor, and sockets and lampholders are connected correctly |
| 6. Earth electrode resistance | On TT systems, the electrode resistance is low enough for the RCD to work |
Live tests, in order
| Test | What it proves |
|---|---|
| 7. Earth fault loop impedance (Ze and Zs) | The fault path is low enough for devices to disconnect in time |
| 8. Prospective fault current | Devices can safely break the highest fault current that can flow |
| 9. RCD operation | Each RCD trips within the required time |
| 10. Phase sequence | On three-phase supplies, the phases are in the right order |
| 11. Functional testing | Switchgear, controls and interlocks work as they should |
Polarity is also confirmed live at the origin with an approved voltage indicator before the installation is energised fully.
If a test fails
Stop, find and fix the fault, then repeat that test and any earlier test the repair could have affected. For example, if you re-terminate a CPC after a failed insulation resistance test, you repeat the continuity test on that circuit as well.
Practise for it
Inspection and testing questions make up most of the 2391 papers and turn up in the AM2 knowledge test. Practise them under time with a worked answer for every question.
Frequently asked questions
What is the correct order of tests in BS 7671?
Dead tests first: continuity of protective conductors, continuity of ring final circuit conductors, insulation resistance, protection by separation, polarity and earth electrode resistance. Then live tests: earth fault loop impedance, prospective fault current, RCD operation, phase sequence and functional testing.
Why are dead tests done before live tests?
Because the dead tests prove the installation is safe to energise. Continuity proves the protective conductors are connected, and insulation resistance proves there are no short circuits or earth faults. Switching on before that could expose you or others to danger.
Is the order of tests mandatory?
BS 7671 lists the tests in a logical order and says that the ones relevant to the installation shall be carried out in that sequence where relevant. If a test fails, you fix the fault and repeat that test and any earlier ones it could affect.
What is the difference between initial verification and periodic inspection?
Initial verification checks a new installation or addition before it is put into service, and is recorded on an Electrical Installation Certificate or Minor Works Certificate. Periodic inspection checks an existing installation for deterioration and is recorded on an Electrical Installation Condition Report (EICR).
What gets recorded on the schedule of test results?
For each circuit: R1 + R2 or R2, ring readings, insulation resistance, polarity, Zs and RCD trip times, along with the circuit details. Ze and prospective fault current are recorded for the installation as a whole.
Related
Sources: BS 7671:2018 as amended, Part 6 and Table 64; IET Guidance Note 3 (Inspection and Testing). FreeMocks is independent and not affiliated with the IET or BSI. Always follow safe isolation and use test equipment that meets HSE GS38.
