EV Charging 2921-34: Vehicle as storage, DNO notification, smart charging and appendices practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

28 of our 112 Electric Vehicle Charging Equipment Installation (2921-34) questions are on vehicle as storage, dno notification, smart charging and appendices, about 25% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. A supply cable to a car park charger is to be run overhead across a road used by vehicles. What minimum height above ground does the Code give?

Show answer

Answer: B. 5.8 m

  • Table K.3 minimum heights:
    • Over roads or subject to vehicular traffic: 5.8 m (ESQCR Reg 17)
    • Uninsulated, not over roads: 5.3 m
    • Insulated, not over roads accessible to vehicles: 4.3 m
  • Avoid unsupported spans where lifting or access equipment is used

Where two classifications apply, the highest figure is used.

Why the others are wrong:

A: 4.3 m is for insulated cables not over roads accessible to vehicles.

C: 5.3 m is the general minimum for uninsulated cables not over roads.

D: 3.5 m is the placing out of reach height, not the height over roads.

Memory trick:

Roads need the most headroom: 5.8.

Find it in the book

IET Code of Practice for EV Charging Equipment Installation, 5th Edition, page 184

Reg CoP Appendix K, Table K.3

Q2. An SWA cable to an on-street charger is buried directly under a highway footway in soft ground. What minimum depth to the top of the cable does the Code recommend?

Show answer

Answer: C. 0.9 m

  • Table K.1: highway footway, verge or bridleway 0.5 m; carriageway 0.6 m
  • Depth is to the top of the duct, or top of cable if earthed armoured cable is buried direct
  • Soft ground: add 400 mm (compression, frost heave, back-fill sinking)
  • 0.5 + 0.4 = 0.9 m

Where two classifications apply, use the deepest.

Why the others are wrong:

A: that adds 400 mm to the carriageway depth of 0.6 m, not the footway depth.

B: 0.5 m is the footway figure before the soft ground allowance is added.

D: 0.6 m is the carriageway figure and still has no soft ground allowance.

The maths

Footway minimum = 0.5 m
Soft ground allowance = 0.4 m
Depth = 0.5 + 0.4 = 0.9 m

Memory trick:

Soft ground? Add 0.4 to whatever the table says.

Find it in the book

IET Code of Practice for EV Charging Equipment Installation, 5th Edition, page 179

Reg CoP Appendix K, Table K.1

Q3. A charger is fed by 25 m of 10 mm2 2-core SWA, armour used as cpc. Conductor 1.83 mOhm/m and armour 6.0 mOhm/m at 20 C; correct to 70 C with 1.20 (copper) and 1.225 (steel), apply 1.1 to the armour, and add 0.3 mOhm/m reactance. With Zdb 0.20 ohm, what is Zs at the charger?

Show answer

Answer: B. 0.46 ohm

  • Resistive part per metre: 1.200 x 1.83 + 1.1 x 1.225 x 6.0 = 10.281 mOhm/m
  • Over 25 m: r = 0.257 ohm; reactance x = 25 x 0.0003 = 0.0075 ohm
  • (Z1 + Z2) = square root of (r squared + x squared) = 0.257 ohm
  • Zs = 0.20 + 0.257 = 0.46 ohm

Only the resistive part is temperature corrected; the reactance is not.

Why the others are wrong:

A: that leaves out the temperature correction factors.

C: that leaves out the 1.1 multiplier on the armour resistance.

D: that is the cable's (Z1 + Z2) only; Zdb must be added.

The maths

r per metre = (1.200 x 1.83) + 1.1 x (1.225 x 6.0) = 2.196 + 8.085 = 10.281 mOhm/m
r = 25 x 0.010281 = 0.257 ohm
x = 25 x 0.0003 = 0.0075 ohm
Z1 + Z2 = sqrt(0.257^2 + 0.0075^2) = 0.257 ohm
Zs = 0.20 + 0.257 = 0.46 ohm

Memory trick:

Correct the copper, correct the steel, times 1.1 on the armour, then add Zdb.

Find it in the book

IET Code of Practice for EV Charging Equipment Installation, 5th Edition, page 192

Reg CoP Appendix M, M2

Q4. A V2H system's inverter and car battery cannot carry the whole house load for the hours needed during a power cut. What does the Code recommend?

Show answer

Answer: B. Load-shedding so only essential low-power loads run

  • Vehicle as storage inverters may not support all loads
  • Large loads will drain the battery early
  • Where the period cannot be covered, load-shedding is recommended
  • Keep essential, low-power loads such as low-energy lighting and communications

Shedding also protects the charge the car needs for the next journey.

Why the others are wrong:

A: the limit is the inverter and battery, not the incoming fuse, which is disconnected in island mode.

C: that would only drain the same limited stored energy; it does not reduce demand.

D: the Code's answer is to shed load, keeping items such as low-energy lighting and communications.

Memory trick:

Island mode: lights and Wi-Fi, not the shower.

Find it in the book

IET Code of Practice for EV Charging Equipment Installation, 5th Edition, page 108

Reg CoP 10.7.5

Q5. A wireless (inductive) charging pad's equipment is installed outdoors on a driveway. What minimum IP rating does the Code recommend for outdoor WPT equipment?

Show answer

Answer: C. IP44

  • Outdoor WPT equipment: at least IP44 to BS EN 60529
  • Ground-mounted parts need a higher IP rating because of submersion or flooding risk
  • In public areas and car parks, protect against impact AG3 (Reg 722.512.2.203)

Note that BS 7671 Section 722 itself excludes inductive charging from its scope, so this guidance comes from the Code.

Why the others are wrong:

A: IP2X gives no protection against water and is far too low for outdoors.

B: the Code gives a full IP44 rating, covering solid objects as well as water.

D: the stated minimum is IP44, with higher ratings needed where ground-mounted parts risk flooding.

Memory trick:

Wireless outdoors: four and four.

Find it in the book

IET Code of Practice for EV Charging Equipment Installation, 5th Edition, page 159

Reg CoP Appendix E, Table E.1

Q6. A V2G charger's supply circuit draws a design current of 20 A when charging (load curtailment applied) and the V2G inverter's rated output is 32 A. What is the minimum OCPD rating In, and what must the cable's Iz be?

Show answer

Answer: C. In at least 32 A, and Iz at least In

  • Cable and OCPD rated so that Iz >= In
  • In selected so that In >= larger of Ib and Ig V2G
  • Ib may take account of load curtailment by the EVSE
  • Here: larger of 20 A and 32 A = 32 A

V2X equipment cannot be a load and a source at once, so the larger figure governs, not the sum.

Why the others are wrong:

A: the two currents are not added, as the circuit cannot charge and discharge at the same time.

B: that sizes on charging current only; In must cover the larger of Ib and the V2G output.

D: Iz must be at least In, not just the design current.

The maths

Ib (charging, curtailed) = 20 A
Ig V2G = 32 A
In >= larger value = 32 A
Iz >= In = 32 A

Memory trick:

Pick the bigger of charge and discharge, then cable to suit.

Find it in the book

IET Code of Practice for EV Charging Equipment Installation, 5th Edition, page 110

Reg CoP 10.7.7 Fig 10.4 Note 4

Want 106 more EV Charging 2921-34 questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other EV Charging 2921-34 topics

Revise this topic