18th Edition: Inspection and testing practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

86 of our 1,080 18th Edition Wiring Regulations (2382-26) questions are on inspection and testing, about 8% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Regulations that come up most

The regulation groups our inspection and testing questions test most often. Know where these are in your book before the exam.

  • 643.7 · 18 questions
  • 643.3 · 10 questions
  • 643.5 · 7 questions
  • 643.1 · 6 questions
  • 644.4 · 4 questions
  • 643.10 · 3 questions
  • 643.4 · 3 questions
  • 644.1 · 3 questions

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. For an IT system, when should the first fault current Id be measured rather than calculated?

Show answer

Answer: B. Only where calculation is impossible as parameters are unknown

  • Id is verified by calculation or measurement
  • Measurement is made only if calculation is not possible
  • Precautions are needed to avoid the danger of a double fault

Measuring deliberately creates a first fault, so it is avoided where possible.

Why the others are wrong:

A: calculation is the preferred method.

C: measurement depends on missing parameters, not the supply source.

D: IMD presence is not the trigger for measurement.

Memory trick:

IT first fault: calculate first, measure as last resort.

Find it in the book

BS 7671:2018+A4:2026, page 251

Reg 643.7.1

Q2. Amendment 4 restructured Part 6 to align with the CENELEC standard. Where has the content of the old Chapters 61, 62 and 63 gone?

Show answer

Answer: C. Into Chapter 64 (initial verification) and Chapter 65 (periodic)

  • A4 deleted Chapters 61, 62 and 63.
  • Their content now forms Chapter 64 Initial verification and Chapter 65 Periodic inspection and testing.

The regulation numbering changed too, so testing regulations now carry 64x numbers (for example 643 Testing) and periodic ones 65x numbers.

Why the others are wrong:

A: Appendix 6 holds the model forms, not the verification requirements themselves.

B: A4 deleted Chapters 61, 62 and 63; their content was moved, not kept in place.

D: periodic inspection and testing has its own new Chapter 65.

Memory trick:

New Part 6: 64 = first time, 65 = every time after.

Find it in the book

BS 7671:2018+A4:2026, page 6

Reg Part 6 (A4 summary of changes)

Q3. Which of the following is a test rather than an item on the minimum inspection checklist of Regulation 642.3?

Show answer

Answer: B. Measurement of earth fault loop impedance

  • The 642.3 inspection list includes items such as fire barriers and seals, danger notices, access to switchgear, labelling, SPDs and isolation devices
  • Earth fault loop impedance is a test (Regulation 643.7.3), not an inspection item

Inspection is by eye and hand; measurements belong to the testing stage.

Why the others are wrong:

A: fire barriers and seals are listed as an inspection item.

C: danger notices and warning signs are listed as an inspection item.

D: access to switchgear is listed as an inspection item.

Memory trick:

If it needs a meter, it is a test, not an inspection.

Find it in the book

BS 7671:2018+A4:2026, page 247

Reg 642.3

Q4. An installation includes an earth electrode. Which test, in addition to the normal dead tests, must be completed before the supply is switched on?

Show answer

Answer: C. Earth electrode resistance

  • Where there is an earth electrode, the test of 643.7.2 (earth electrode resistance) must also be done before energizing

Without a proven electrode in a TT system there is no reliable fault path, so it is checked before the supply goes on.

Why the others are wrong:

A: this is not required before energizing and is normally measured with the supply on.

B: an RCD can only be tested with the supply on.

D: phase rotation is checked with the installation live.

Memory trick:

No electrode proof, no power on.

Find it in the book

BS 7671:2018+A4:2026, page 248

Reg 643.1

Q5. During a periodic inspection, a thermal imaging camera shows a hot busbar joint. How does Chapter 65 (A4) treat the images?

Show answer

Answer: A. They can be attached to the report to support that observation

  • A4 added a note to 653.2: photographic and/or thermographic images can be attached to the report.
  • They support observations made in the relevant section of the model form (Section K).

The observation still needs a code (C1, C2, C3 or FI) in the normal way.

Why the others are wrong:

B: a note added by A4 says photographic and thermographic images can be attached.

C: images only support an observation; it still needs its code.

D: there is no such requirement; the images go with the report.

Memory trick:

A picture backs up a code, it never replaces one.

Find it in the book

BS 7671:2018+A4:2026, page 255

Reg 653.2 NOTE

Q6. How is periodic inspection normally carried out?

Show answer

Answer: B. Without dismantling, or with partial dismantling, plus appropriate tests

  • Periodic inspection: without dismantling, or with partial dismantling as required
  • Supplemented by appropriate tests and measurements from Chapter 64
  • Purpose includes safety against shock and burns, fire risk, correct device ratings and identifying defects

Periodic work is a sample-based health check, not a strip-down.

Why the others are wrong:

A: full dismantling is not required; partial as needed.

C: inspection is supplemented by appropriate tests and measurements from Chapter 64.

D: no such requirement is stated.

Memory trick:

Periodic: look and sample, do not strip.

Find it in the book

BS 7671:2018+A4:2026, page 254

Reg 651.2

Want 1,074 more 18th Edition questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.