ACS CCN1: Ventilation practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

33 of our 270 ACS CCN1 Core Domestic Gas Safety (ACS-CCN1) questions are on ventilation, about 12% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. For which of these installations must you NOT include any adventitious air allowance when sizing ventilation?

Show answer

Answer: A. A boiler installed in a compartment

  • Adventitious air is not taken into account for:
    • flueless appliances
    • appliances in compartments
    • DFE gas appliances

Compartments use the total maximum rated heat input with no deduction.

Why the others are wrong:

B: an open-flued appliance in a room does get the first 7kW allowance.

C: adventitious air is relied on here; no vent is normally needed.

D: one appliance in a multi-appliance room still gets the allowance.

Memory trick:

Flueless, compartment, DFE: no free air for them.

Find it in the book

CORGI GID1, 10th Edition, Volume 1, page 85

Reg GID1 Part 4, Adventitious ventilation

Q2. Where may an air vent that supplies an open-flued appliance NOT communicate?

Show answer

Answer: C. A room containing a bath or shower

  • An air vent supplying an open-flued appliance should not communicate with any room or space containing a bath or shower
  • It also must not penetrate a protected shaft or communicate with an underfloor space shared with other premises

Bath and shower rooms often have extract fans and are humid.

Why the others are wrong:

A: feeding through an adjacent ventilated room is permitted.

B: that can be treated as outside air if its vents are adequate and clear.

D: vents can pass through an adjacent room provided that room is suitably ventilated.

Memory trick:

Open flue and bathroom air never mix.

Find it in the book

CORGI GID1, 10th Edition, Volume 1, page 87

Reg GID1 Part 4, Ventilation openings and grilles

Q3. A customer wants to fit a fly screen and a closable flap to the new air vent for their open-flued boiler. What do you tell them?

Show answer

Answer: C. Neither is allowed: the vent must be non-closable with no added gauze or screen

  • Air vents should be non-closable
  • They should not incorporate additional gauze or screens
  • Outside vents should be as high as reasonably practicable to avoid blockage

Screens clog and flaps get closed, starving the appliance of air.

Why the others are wrong:

A: vents should not incorporate any additional gauze or screens.

B: vents should be non-closable at all times.

D: oversizing does not make a closable or screened vent acceptable.

Memory trick:

No flaps, no mesh.

Find it in the book

CORGI GID1, 10th Edition, Volume 1, page 86

Reg GID1 Part 4, Ventilation openings and grilles

Q4. After a small kitchen fire you find the intumescent air vent serving the open-flued boiler has expanded and closed. What must happen before the boiler is used?

Show answer

Answer: B. The intumescent vent must be replaced

  • Intumescent vents expand and close in extreme heat to stop smoke spreading
  • One that has been triggered must be replaced before any gas appliance is operated
  • It must have no manual closing device

Check existing ones are fully open and give the required free area.

Why the others are wrong:

A: once triggered it cannot be relied on and must be replaced.

C: a vent was needed, so adventitious air is not enough.

D: intumescent vents must have no means of closing other than by fire.

Memory trick:

Once it pops, it's swapped.

Find it in the book

CORGI GID1, 10th Edition, Volume 1, page 90

Reg GID1 Part 4, Intumescent air vents

Q5. A boiler is in an under-stairs cupboard in a three-storey house. Where must its compartment vents go?

Show answer

Answer: B. Direct to outside air

  • Under-stairs vent sizes follow the compartment requirements
  • Premises more than two storeys: vents must be direct to outside air
  • Up to and including two storeys: may vent to a room or internal space

A room-sealed boiler is preferred there, and it should be a last resort location.

Why the others are wrong:

A: venting into a room is only allowed up to two storeys.

C: new vents must not communicate with a roof space.

D: under-stairs cupboards follow the compartment rules.

Memory trick:

Over two floors, under the stairs: vent outside.

Find it in the book

CORGI GID1, 10th Edition, Volume 1, page 105

Reg GID1 Part 4, Under-stairs cupboard ventilation

Q6. An existing open-flued appliance takes air through a duct from a ventilated loft. Where must the duct's roof space terminal sit to avoid being blocked by insulation?

Show answer

Answer: C. At least 300mm above the joists or 150mm above the insulation, whichever is greater

  • Terminal not less than 300mm above joists or 150mm above insulation, whichever is greater
  • Measured to the bottom openings of the terminal
  • A data plate or notice should state the clearances

Loft insulation is often topped up later, so the notice protects the air supply.

Why the others are wrong:

A: flush terminals are easily buried by insulation.

B: the figures are reversed and it is the greater of the two that applies.

D: 450mm is the internal wall vent limit, not a loft duct clearance.

Memory trick:

Three hundred over joists, one fifty over fluff.

Find it in the book

CORGI GID1, 10th Edition, Volume 1, page 99

Reg GID1 Part 4, Air supply from roof spaces