Part P 2393-10: Ventilation, energy, access and EV charging (AD F, L, M, S) practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

55 of our 160 Building Regulations for Electrical Installations in Dwellings (Part P) (2393-10) questions are on ventilation, energy, access and ev charging (ad f, l, m, s), about 34% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. On a new development the DNO quote shows the average extra connection cost would be £4,200 per charge point if every required space got one. What should happen?

Show answer

Answer: B. Fit as many as stay within £3,600 average, with cable routes for the rest

  • Charge points required = the maximum number that can be installed at an average connection cost of £3,600 or less each.
  • Spaces that would have needed a charge point but for the cap get cable routes instead.
  • Connection cost excludes VAT, building work and the charge point itself.

Why the others are wrong:

A: the cap limits the number of charge points; cable routes are still needed for the spaces that miss out.

C: the regulations set the number at the maximum possible within the £3,600 cap.

D: there is no 50% rule; spaces missing out because of the cap need cable routes.

Memory trick:

Over £3,600: fit what the cap allows, cable the rest.

Reg Approved Document S, Regulation 44D and 1.6

Q2. A fitting is specified to deliver 1800 light source lumens. What is the highest circuit wattage it can draw and still meet the Approved Document L minimum efficacy for internal lighting?

Show answer

Answer: B. 24 W

  • Efficacy = lumens / circuit-watts, so maximum watts = lumens / 75.
  • 1800 / 75 = 24 W.
  • Any more than 24 circuit-watts drops the fitting below 75 lm/W.

Why the others are wrong:

A: this uses 80 lm/W, the notional dwelling figure, rather than the 75 lm/W minimum.

C: this would give only 60 lm/W, below the minimum.

D: this assumes 100 lm/W; it would pass, but it is not the highest wattage allowed.

The maths

Step 1: Minimum efficacy = 75 lm per circuit-watt.
Step 2: Maximum circuit-watts = 1800 / 75 = 24 W.
Check: 1800 / 24 = 75 lm/W (just complies).

Memory trick:

Max watts = lumens divided by 75.

Reg Approved Document L Vol 1, 6.58

Q3. A new block of 8 flats has 12 associated open-air parking spaces. The connection cost is within the cap. What EV provision is required?

Show answer

Answer: A. 8 spaces with charge points and cable routes to the other 4

  • More spaces (12) than dwellings (8): charge points for a number of spaces equal to the number of dwellings = 8.
  • Spaces more than 10 and more spaces than dwellings: cable routes to all remaining spaces = 4.

Why the others are wrong:

B: charge points are needed for as many spaces as there are dwellings, i.e. 8, not every space.

C: there are more than 10 spaces and more spaces than dwellings, so the remaining spaces need cable routes.

D: the number of charge points equals the number of dwellings (8) when spaces outnumber dwellings.

The maths

Step 1: Spaces (12) >= dwellings (8), so charge points = 8.
Step 2: Spaces > 10 and spaces > dwellings, so cable routes go to the rest.
Step 3: 12 - 8 = 4 spaces with cable routes.

Memory trick:

Charge points = dwellings; over 10 spaces, cable the rest.

Reg Approved Document S, Requirement S1 and 1.1 to 1.3

Q4. What may a building control body do if it has not received the notice confirming commissioning of the fixed building services?

Show answer

Answer: B. Decide not to issue a completion certificate

  • A commissioning notice must be given confirming fixed building services have been commissioned.
  • Until the building control body receives it, it may decide not to give a completion/final certificate.

A missing notice can hold up sign-off of the whole job.

Why the others are wrong:

A: the guidance gives no power to order disconnection for a missing notice.

C: this is not what the guidance describes.

D: the commissioning notice must be given; it is not optional.

Memory trick:

No commissioning notice, no completion certificate.

Find it in the book

Approved Document L Volume 1 (2021 edition incl. 2023 amendments), para 8.7, page 55

Reg Approved Document L Vol 1, 8.7

Q5. A new building contains 9 flats and has 10 associated open-air parking spaces. The connection cost is within the cap. What EV provision is required?

Show answer

Answer: D. 9 charge points, no cable route required

  • Spaces (10) are more than dwellings (9), so charge points = 9.
  • Cable routes to the remaining spaces apply only if there are more than 10 associated spaces and more spaces than dwellings.
  • 10 is not more than 10, so no cable route is required to the spare space.

Why the others are wrong:

A: there is no 50% rule; the number of charge points equals the number of dwellings.

B: charge points are only required for a number of spaces equal to the number of dwellings.

C: cable routes for the remaining spaces are only required where there are more than 10 spaces.

The maths

Step 1: Spaces (10) >= dwellings (9): charge points = 9.
Step 2: Cable route test: spaces > 10? 10 is not > 10, so the test fails.
Step 3: Result: 9 charge points, no cable route required for the 10th space.

Memory trick:

Ten is not over ten: no compulsory cable route.

Reg Approved Document S, Requirement S1(2) and S1(3)

Q6. A boiler is being replaced and a room thermostat is fitted in the lounge. Which arrangement of thermostatic radiator valves (TRVs) meets the Approved Document L guidance?

Show answer

Answer: C. TRVs on all radiators except those in the lounge

  • One accepted method: a room thermostat in a room the circuit serves, plus a TRV (or similar) on every heat emitter outside that room.
  • TRVs should not be used in the same room as the thermostat.

A TRV fighting the room thermostat can stop the thermostat ever being satisfied.

Why the others are wrong:

A: each room needs its own thermostatic control; other rooms need TRVs or similar.

B: TRVs should not be used in the same room as the room thermostat.

D: all heat emitters outside the thermostat's room need individual thermostatic control.

Memory trick:

Stat or TRV per room, never both in the same room.

Reg Approved Document L Vol 1, 5.22

Want 154 more Part P 2393-10 questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other Part P 2393-10 topics

Revise this topic