Q1. On a new development the DNO quote shows the average extra connection cost would be £4,200 per charge point if every required space got one. What should happen?
Show answer
Answer: B. Fit as many as stay within £3,600 average, with cable routes for the rest
- Charge points required = the maximum number that can be installed at an average connection cost of £3,600 or less each.
- Spaces that would have needed a charge point but for the cap get cable routes instead.
- Connection cost excludes VAT, building work and the charge point itself.
Why the others are wrong:
A: the cap limits the number of charge points; cable routes are still needed for the spaces that miss out.
C: the regulations set the number at the maximum possible within the £3,600 cap.
D: there is no 50% rule; spaces missing out because of the cap need cable routes.
Memory trick:
Over £3,600: fit what the cap allows, cable the rest.