Q1. Which of these may pass through an opening in a cavity barrier, according to Approved Document B?

Show answer

Answer: D. Cables, or conduits containing cables

  • AD B 5.24 limits openings in cavity barriers to:
    • fire doorsets (minimum E 30)
    • pipes following Section 9
    • cables or conduits containing one or more cables
    • openings with a fire damper
    • fire resisting ducts, or ducts fitted with a fire damper

The opening around the cable should still be kept small and sealed.

Why the others are wrong:

A: openings are limited to specific items; spare unsealed gaps are not one of them.

B: ducts and openings need fire resistance or a suitable fire damper.

C: doors in cavity barriers must be fire doorsets of at least E 30.

Memory trick:

Cables can cross the barrier; open gaps cannot.

Reg Approved Document B Vol 1, 5.24

Q2. A cavity wall meeting Diagram 5.3 (excluded from cavity barrier provisions) is to have external domestic meter cupboards. Which condition does Approved Document B set?

Show answer

Answer: C. No more than two cupboards per dwelling

  • Diagram 5.3 note 2: domestic meter cupboards may be installed if:
    • there are no more than two cupboards per dwelling
    • the outer leaf opening for each is no bigger than 800 x 500mm
    • the inner leaf is only penetrated by a sleeve no more than 80 x 80mm, fire-stopped

This keeps the cavity wall within the conditions that exempt it from cavity barriers.

Why the others are wrong:

A: four exceeds the limit; the maximum is two.

B: Diagram 5.3 allows up to two cupboards per dwelling.

D: the number is limited to two and the conditions relate to opening and sleeve sizes.

Memory trick:

Two boxes, 800 by 500, one 80 by 80 sleeve.

Reg Approved Document B Vol 1, Diagram 5.3

Q3. What is the minimum standard of fire detection and alarm system that Approved Document B recommends for all dwellings?

Show answer

Answer: A. Grade D2 Category LD3, to BS 5839-6

  • AD B 1.1: every dwelling should have a system of minimum Grade D2 Category LD3.
  • It should follow the recommendations of BS 5839-6.

A higher standard should be considered where occupants would be at special risk from fire.

Why the others are wrong:

B: Grade A LD2 is what AD B gives for large dwellinghouses of three or more storeys, not the minimum for all dwellings.

C: Grade F uses battery-only alarms; AD B sets Grade D2 as the minimum.

D: LD1 is a higher category and BS 5839-1 covers non-domestic systems.

Memory trick:

D2 LD3: the domestic default.

Reg Approved Document B Vol 1, 1.1

Q4. A large dwellinghouse has three storeys above ground plus a basement. What system does Approved Document B recommend?

Show answer

Answer: A. Grade A Category LD2

  • Basement storeys are excluded from the storey count.
  • Three or more storeys: Grade A Category LD2 (AD B 1.7).

LD2 adds detection in rooms with a higher fire risk, on top of the circulation spaces covered by LD3.

Why the others are wrong:

B: LD3 is for large dwellinghouses of two storeys; this house has three storeys excluding the basement.

C: D2 LD3 is the minimum for ordinary dwellings, not large ones.

D: large dwellinghouses need a Grade A system.

Memory trick:

More storeys, more cover: three storeys gets LD2.

Reg Approved Document B Vol 1, 1.7

Q5. An electrician runs a cable from a house into its integral garage through the separating wall. What does Approved Document B require?

Show answer

Answer: A. Keep the wall REI 30 and fire-stop the cable hole

  • AD B 5.6: an attached or integral garage should be separated from the dwellinghouse by fire resisting construction, minimum REI 30 (from the garage side, Diagram 5.1).
  • AD B 9.24: openings for cables should be as few and small as possible and fire-stopped.

The cable must not create a weak point in the separating wall.

Why the others are wrong:

B: AD B requires REI 30 separation between an integral garage and the house.

C: the minimum is REI 30, and AD B does not require steel conduit.

D: the opening must be fire-stopped and the wall's REI 30 maintained.

Memory trick:

Garage wall: thirty minutes, sealed around every cable.

Reg Approved Document B Vol 1, 5.6 and 9.24

Q6. An external cavity wall must resist rain reaching the inner leaf. Which items does Approved Document C accept as bridging the cavity?

Show answer

Answer: A. Wall ties, cavity trays, cavity barriers and closures

  • AD C 5.13(b): the cavity (at least 50mm wide) is to be bridged only by wall ties, cavity trays, and cavity barriers, firestops and cavity closures where appropriate.

Anything else spanning the cavity, such as battens or mortar, can carry rain to the inner leaf. Cable entries should pass through without forming a bridge.

Why the others are wrong:

B: a batten across the cavity is not one of the permitted bridges and can carry water inwards.

C: a mortared duct forms a solid bridge, which AD C does not list.

D: mortar droppings bridge the cavity and let moisture across.

Memory trick:

Ties, trays and barriers: nothing else crosses the cavity.

Reg Approved Document C, 5.13(b)

Want 154 more Part P 2393-10 questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other Part P 2393-10 topics

Revise this topic