Part P 2393-10: Building Regulations framework practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

23 of our 160 Building Regulations for Electrical Installations in Dwellings (Part P) (2393-10) questions are on building regulations framework, about 14% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. A contractor deposits a building notice and informs the local authority on Monday 12 October 2026 of their intention to start. With no bank holidays, what is the earliest day work may begin?

Show answer

Answer: C. Thursday 15 October 2026

  • Two clear working days' notice must be given before work starts (regulation 16(1)).
  • Informed Monday; Tuesday and Wednesday are the clear days.
  • Work may start on Thursday, the third day after the authority was informed.

"Clear" means the day of notice and the start day do not count.

Why the others are wrong:

A: only one clear working day (Tuesday) has passed by then.

B: work cannot start on the same day; two clear working days' notice is needed.

D: this allows a full working week, more than the two clear days required.

The maths

  1. Notice given: Monday 12 October.
  2. Clear working day 1: Tuesday 13 October.
  3. Clear working day 2: Wednesday 14 October.
  4. Earliest start: Thursday 15 October 2026.

Memory trick:

Tell on day 0, two clear days, start on day 3.

Reg Manual to the Building Regulations, D14 and D20

Q2. Regulation 7 sets the basic standard for materials and workmanship. What does it require?

Show answer

Answer: D. Adequate and proper materials, in a workmanlike manner

  • Regulation 7: building work must be carried out with adequate and proper materials and in a workmanlike manner.
  • Materials must suit the circumstances, be properly prepared and be fixed so they perform as designed.

It applies to all building work covered by the Regulations.

Why the others are wrong:

A: regulation 7 does not require a chartered engineer.

B: regulation 7 says nothing about guarantees.

C: there is no general prior approval requirement for materials.

Memory trick:

Reg 7: proper stuff, properly done.

Reg Manual to the Building Regulations, F9

Q3. A customer has planning permission for an extension and assumes no Building Regulations approval is needed. What does the Manual say?

Show answer

Answer: D. Planning and Building Regulations approval are separate, and both may be needed

  • Building Regulations approval is different from planning permission and listed building consent.
  • You could need all three.
  • Work under permitted development rights is still likely to need building control.

Always check both regimes before starting.

Why the others are wrong:

A: the two systems operate independently.

B: Building Regulations approval is different from planning permission.

C: permitted development work is still likely to go through building control.

Memory trick:

Planning says where and what; Building Regs say how.

Reg Manual to the Building Regulations, Chapter 3

Q4. Most building work must be notified to a building control body. Which of these is one of the stated exceptions?

Show answer

Answer: C. Work exempted from notification by Schedule 4

  • Notification is not needed where the work is:
    • self-certified by a registered competent person
    • certified by a registered third party
    • exempted by regulation 12(6A) or Schedule 4

Schedule 4 lists work that need not be notified, but it must still comply.

Why the others are wrong:

A: the time taken does not affect whether work is notifiable.

B: there is no cost threshold for notification.

D: the owner cannot waive notification.

Memory trick:

Competent person, third party, or Schedule 4: the three ways out of notifying.

Reg Approved Document P, Building Regulations summary (notification)

Q5. If the building owner or those carrying out building work contravene the Building Regulations, where may the local authority prosecute, and what fine is possible?

Show answer

Answer: B. Magistrates' court, with an unlimited fine

  • Under Sections 35 and 35A of the Building Act, the local authority may prosecute in the magistrates' court.
  • An unlimited fine may be imposed.
  • The authority can also require works to be pulled down or removed.

Both owners and those doing the work can be pursued.

Why the others are wrong:

A: the manual refers to the magistrates' court and an unlimited fine.

C: prosecution is in the magistrates' court and the fine is unlimited.

D: the manual describes prosecution and fines, not a tribunal ban.

Memory trick:

Break the regs, face the magistrates, no ceiling on the fine.

Reg Manual to the Building Regulations, B12

Q6. Under regulation 8, for Part P the standards of materials and workmanship need be no higher than necessary to achieve what?

Show answer

Answer: D. Reasonable standards of health or safety for people in or about the building

  • Regulation 8 limits how high the standards need be.
  • For Parts A to D, F to K and P: to secure reasonable standards of health or safety.
  • Part E: sound. Part L: fuel and power. Part M: access.

Part P is a safety Part, so health and safety is the yardstick.

Why the others are wrong:

A: that is the purpose for Part M.

B: that is the purpose for Part L.

C: that is the purpose for Part E.

Memory trick:

P is for protection: health and safety is the bar.

Reg Manual to the Building Regulations, F11 (reg 8)

Want 154 more Part P 2393-10 questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other Part P 2393-10 topics

Revise this topic