Q1. A contractor deposits a building notice and informs the local authority on Monday 12 October 2026 of their intention to start. With no bank holidays, what is the earliest day work may begin?
Show answer
Answer: C. Thursday 15 October 2026
- Two clear working days' notice must be given before work starts (regulation 16(1)).
- Informed Monday; Tuesday and Wednesday are the clear days.
- Work may start on Thursday, the third day after the authority was informed.
"Clear" means the day of notice and the start day do not count.
Why the others are wrong:
A: only one clear working day (Tuesday) has passed by then.
B: work cannot start on the same day; two clear working days' notice is needed.
D: this allows a full working week, more than the two clear days required.
The maths
- Notice given: Monday 12 October.
- Clear working day 1: Tuesday 13 October.
- Clear working day 2: Wednesday 14 October.
- Earliest start: Thursday 15 October 2026.
Memory trick:
Tell on day 0, two clear days, start on day 3.