Q1. Why is commissioning described as one of the few quality controls on a building services installation?
Show answer
Answer: B. Design or equipment failures become apparent when systems are run
- During commissioning, any design or equipment failures become apparent.
- This testing is one of the few quality controls possible on a building services installation.
Running the systems shows whether they really work.
Why the others are wrong:
A: inspection happens before testing.
C: the EIC is still required.
D: it is carried out by the commissioning engineer.
Memory trick:
Switch it on and the truth comes out.
Find it in the book
Linsley, Electrical Installation Work Level 3 (EAL Edition), page 297