QELTK3/006: Commissioning and handover practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

19 of our 180 Inspection, Testing, Commissioning and Certification (QELTK3-006) questions are on commissioning and handover, about 11% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Regulations that come up most

The regulation groups our commissioning and handover questions test most often. Know where these are in your book before the exam.

  • 643.10 · 5 questions
  • 514.9 · 1 questions
  • 653.2 · 1 questions

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. Why is commissioning described as one of the few quality controls on a building services installation?

Show answer

Answer: B. Design or equipment failures become apparent when systems are run

  • During commissioning, any design or equipment failures become apparent.
  • This testing is one of the few quality controls possible on a building services installation.

Running the systems shows whether they really work.

Why the others are wrong:

A: inspection happens before testing.

C: the EIC is still required.

D: it is carried out by the commissioning engineer.

Memory trick:

Switch it on and the truth comes out.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 297

Reg EAL Ch4 commissioning

Q2. Regulation 643.10 gives examples of equipment that should be functionally tested. Which of these is NOT one of its examples?

Show answer

Answer: C. Cable insulation between line and earth

  • Regulation 643.10 requires equipment to be functionally tested to check it is properly mounted, adjusted and installed and operates correctly.
  • Its examples are switchgear and controlgear assemblies, drives, controls and interlocks; emergency switching off and emergency stopping; and insulation monitoring.
  • Cable insulation is checked by the insulation resistance test (643.3), not a functional test.

Functional testing asks: does it work as intended when operated?

Why the others are wrong:

A: this is listed as an example in 643.10.

B: this is listed as an example in 643.10.

D: this is listed as an example in 643.10.

Memory trick:

Functional = does it WORK, not is it insulated.

Find it in the book

BS 7671:2018+A4:2026, page 252

Reg 643.10

Q3. Which of these systems would a commissioning engineer NOT normally be testing as part of electrical commissioning?

Show answer

Answer: A. Floor slab load capacity

  • The commissioning engineer tests all electrical systems, including motor controls, fans and air conditioning, fire alarms and emergency lighting.
  • Structural testing is outside electrical commissioning.

If it is powered or controlled electrically, it is commissioned.

Why the others are wrong:

B: these are listed systems.

C: these are listed systems.

D: this is a listed system.

Memory trick:

Motors, fans, alarms, emergency lights.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 297

Reg EAL Ch4 commissioning

Q4. A hotel's facilities manager is setting up routine checks of the electrical installation between formal inspections. Which statement about these checks is correct?

Show answer

Answer: D. They need not be done by an electrically skilled person

  • GN3 says installations should not be left without attention for the years between formal inspections.
  • Routine checks need not be carried out by an electrically skilled person, but by someone able to safely use the installation and recognize defects.
  • Their frequency is set by the electrical dutyholder, and a simple form to record defects is all that is needed.

The client should be told this at handover so checks actually happen.

Why the others are wrong:

A: commercial and industrial premises under the EAWR need formal routine checks.

B: routine checks can be done by anyone able to use the installation safely and recognize defects.

C: routine checks happen between formal inspections; they do not replace them.

Memory trick:

Routine checks: a careful user, not necessarily a sparky.

Find it in the book

IET Guidance Note 3 (2022 edition), page 113

Reg GN3 3.5; HSR25

Q5. A main circuit-breaker is interlocked with an outgoing switch so they cannot both be closed. Checking the interlock is beyond the inspector's knowledge. What does GN3 suggest?

Show answer

Answer: B. Refer it to the manufacturer or a specialist

  • GN3 says where any form of interlocking is provided, its integrity must be verified.
  • It accepts this may be beyond the scope of the inspector, and can be referred to a manufacturer or specialist.
  • Mechanical maintenance switching must also be checked to make sure equipment cannot be unintentionally re-energized.

Interlocks prevent dangerous combinations, so they must be proved, not presumed.

Why the others are wrong:

A: the integrity of interlocking must be verified, not assumed from appearance.

C: dismantling the interlock could create danger and does not verify it.

D: the interlock is present, so its integrity must be verified.

Memory trick:

Can't prove the interlock? Call the maker.

Find it in the book

IET Guidance Note 3 (2022 edition), page 132

Reg 643.10; GN3 2.6.19

Q6. For a new-build house, what does NHBC guidance, as quoted in GN3, recommend about information on the building's services?

Show answer

Answer: B. All instructions for the services go to the owner

  • GN3 says that for domestic installations, NHBC guidance recommends that all instructions for services are passed to the building owner.
  • For non-domestic work, the CDM health and safety file plays a similar role.
  • There may also be insurance requirements for records.

The owner cannot operate or maintain equipment safely without its instructions.

Why the others are wrong:

A: the guidance is for the owner to have the instructions, not the builder.

C: the guidance covers all instructions for services, not just the certificate.

D: the owner needs the instructions to use and maintain the services.

Memory trick:

New home, full handover pack.

Find it in the book

IET Guidance Note 3 (2022 edition), page 18

Reg GN3 1.6