Q1. You are the only contractor on a small project. Who must draw up the construction phase plan?
Show answer
Answer: C. You, before setting up the construction site
- If there is only one contractor, the contractor must draw up a construction phase plan, or arrange for one, as soon as practicable before setting up the site.
- The client must provide relevant pre-construction information.
The plan can be short for small, low-risk jobs.
Why the others are wrong:
A: on single contractor projects the contractor draws up the plan.
B: HSE does not write construction phase plans.
D: a construction phase plan is needed on every project.
Memory trick:
One contractor: you write the plan.
Find it in the book
HSE L153 (CDM 2015), page 43