CITB Refrigeration and AC: Core: environment practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

16 of our 200 CITB HS&E Specialist Test: Refrigeration and Air Conditioning (CITB-SPEC-RAAC) questions are on core: environment, about 8% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. You have recovered waste F gas into a cylinder. How must it be sent for reclaim or destruction?

Show answer

Answer: D. Registered waste carrier to a licensed facility

  • You must use a registered waste carrier to send recovered waste F gas (or the whole unit) to a licensed waste facility that accepts waste F gas and ozone-depleting substances (ODS).
  • The facility can reclaim, recycle or destroy it.

Record the waste carrier used in the equipment records.

Why the others are wrong:

A: it must go via a registered waste carrier to a licensed facility.

B: the guidance names licensed waste facilities, not manufacturers.

C: F gas waste must go to a facility that accepts F gas and ODS.

Memory trick:

Registered carrier, licensed facility.

Find it in the book

Recovering, reclaiming and recycling F gas

Reg GOV.UK F gas guidance: Recovering, reclaiming and recycling F gas (updated 18 April 2023)

Q2. You must cut a steel bracket with a disc cutter beside a public footpath. What does HSG150 say?

Show answer

Answer: D. Fence it off to contain dust and sparks

  • Fence off hot work, such as welding or the use of disc cutters, to contain dust and sparks.
  • Bitumen and similar boilers in public spaces should also be fenced off.

The public must be protected from your work.

Why the others are wrong:

A: the public must be protected throughout, not just when passing.

B: relying on the public is not a control measure.

C: the guidance is to fence off hot work to contain dust and sparks.

Memory trick:

Public nearby: fence the sparks in.

Find it in the book

HSE HSG150 (2006), page 109

Reg HSE HSG150, para 563

Q3. Your site has had arson attacks nearby. Where does HSG168 suggest keeping waste skips and materials?

Show answer

Answer: C. In a secure compound or away from the perimeter

  • Store materials and waste within the site perimeter, preferably in secure compounds or away from the perimeter fencing.
  • Skips are often a target and their vulnerability should be considered.

Good security and lighting reduce arson risk.

Why the others are wrong:

A: skips are often targeted and should be kept away from the fence.

B: this makes them easy targets.

D: vulnerable buildings should not be filled with fuel for a fire.

Memory trick:

Keep skips away from the fence.

Find it in the book

HSE HSG168 (3rd edition, 2022), page 28

Reg HSE HSG168 (3rd edition, 2022), para 142

Q4. Your site needs an external store for flammable liquids. What enclosure does HSG168 suggest?

Show answer

Answer: B. A 1.8 m high wire mesh fence

  • Storage areas should be in the open air and well ventilated.
  • External stores should be enclosed by a 1.8 m high wire mesh fence to give security without restricting ventilation.

Keep stores away from buildings and ignition sources.

Why the others are wrong:

A: an enclosed timber shed restricts ventilation and can burn.

C: an unventilated container lets vapour build up.

D: tape gives no security and is not the guidance.

Memory trick:

Mesh fence, open air.

Find it in the book

HSE HSG168 (3rd edition, 2022), page 29

Reg HSE HSG168 (3rd edition, 2022), para 149

Q5. At the end of a strip-out, someone suggests burning the packaging and timber waste on site. What does HSG168 say?

Show answer

Answer: A. Do not burn trade waste or rubbish on site

  • Do not burn trade waste or rubbish on site.
  • Burning vegetation or untreated wood should only be considered in very limited situations, with permits.

Use proper waste skips and a registered waste carrier.

Why the others are wrong:

B: HSG168 says not to burn trade waste on site at all.

C: burning out of hours is even riskier.

D: trade waste should not be burned on site.

Memory trick:

Skip it, don't burn it.

Find it in the book

HSE HSG168 (3rd edition, 2022), page 27

Reg HSE HSG168 (3rd edition, 2022), para 138

Q6. In the rare cases where burning material on site may be permitted, what must contractors do first?

Show answer

Answer: B. Ask the client, council and EA; get a permit

  • Contractors must check with clients, local authorities and the Environment Agency (or SEPA in Scotland).
  • They must obtain the relevant permit before burning any material on site.

Environmental law governs the rare cases where burning is allowed.

Why the others are wrong:

A: permission and a permit are needed, not just notice to neighbours.

C: weather is a precaution, but a permit is needed first.

D: precautions don't replace the permit.

Memory trick:

No permit, no fire.

Find it in the book

HSE HSG168 (3rd edition, 2022), page 27

Reg HSE HSG168 (3rd edition, 2022), para 139

Want 194 more CITB Refrigeration and AC questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other CITB Refrigeration and AC topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (HSE). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic