CITB Plumbing (JIB): Water hygiene and legionella practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

40 of our 200 CITB HS&E Specialist Test: Plumbing (JIB) (CITB-SPEC-PLUM) questions are on water hygiene and legionella, about 20% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. Which illness is a less serious form of legionellosis?

Show answer

Answer: D. Pontiac fever

  • Legionellosis covers diseases caused by legionella, including Legionnaires' disease (the most serious).
  • Pontiac fever and Lochgoilhead fever are similar but less serious conditions.

Legionnaires' disease itself is a potentially fatal pneumonia.

Why the others are wrong:

A: tetanus is not a form of legionellosis.

B: Weil's disease is not caused by legionella bacteria.

C: silicosis is a lung disease caused by silica dust.

Memory trick:

Pontiac: legionella's milder cousin.

Find it in the book

HSE L8 (4th edition, 2013), page 6

Reg HSE L8 ACOP, guidance paragraph 10

Q2. How long should records of legionella monitoring, inspections, tests and checks be kept?

Show answer

Answer: B. At least five years

  • Records of any monitoring, inspection, test or check, with dates, should be kept for at least five years.
  • Other records should be kept while current and for at least two years afterwards.

Records should be signed or otherwise authenticated by the person doing the work.

Why the others are wrong:

A: this is shorter than the ACOP requires.

C: two years after they stop being current applies to other records such as the scheme.

D: the ACOP sets a minimum retention period.

Memory trick:

Monitoring logs: keep for five.

Find it in the book

HSE L8 (4th edition, 2013), page 19

Reg HSE L8 ACOP, paragraph 72

Q3. A shower in a building is no longer needed. What should be done with its supply pipework?

Show answer

Answer: C. Cut it back to the common supply, ideally removing the tee

  • Consider removing infrequently used showers and taps.
  • Cut redundant pipework back as far as possible to a common supply, preferably by removing the feeding tee.

High-risk settings, such as care homes, may need more frequent flushing.

Why the others are wrong:

A: this leaves a dead leg where water stagnates.

B: annual flushing is not enough and the outlet should be removed.

D: a check valve does not remove the stagnant length of pipe.

Memory trick:

Dead shower? Cut it back to the tee.

Find it in the book

HSE HSG274 Part 2, page 78

Reg HSE HSG274 Part 2, paragraph 2.77 and Table 2.1

Q4. A water system is being disinfected with chlorine. What is the normal dose and contact time?

Show answer

Answer: B. 50 ppm for at least one hour, ending at 30 ppm or more

  • Disinfection is normally chlorine at 50 ppm for a minimum contact period of one hour.
  • At the end, the concentration should be not less than 30 ppm free residual chlorine.

Lower concentrations with longer contact times are acceptable as set out in BS 8558.

Why the others are wrong:

A: these are not the figures in the guidance.

C: the figures are reversed: dose 50 ppm, residual not below 30 ppm.

D: this is far weaker and shorter than the normal regime.

Memory trick:

50 in, an hour on, 30 left.

Find it in the book

HSE HSG274 Part 2, page 88

Reg HSE HSG274 Part 2, paragraph 2.135

Q5. In an office with a circulating hot water system, what is the lowest acceptable return temperature at the calorifier?

Show answer

Answer: A. 50 °C

  • Calorifier flow should be as close to 60 °C as practicable without going below it.
  • Calorifier return temperatures should be not below 50 °C.

Flow and return temperatures are checked monthly.

Why the others are wrong:

B: 45 °C is the top of the growth range, not the control figure.

C: 40 °C is inside the growth range.

D: 60 °C is the flow (storage) target, not the minimum return.

Memory trick:

Out at 60, back at 50.

Find it in the book

HSE HSG274 Part 2, page 76

Reg HSE HSG274 Part 2, Table 2.1 (calorifiers)

Q6. During thermal disinfection of a hot water system, what is needed at each outlet?

Show answer

Answer: A. At least 60 °C, run for at least five minutes

  • Raise the calorifier contents and circulate for at least an hour, then flush every outlet so the outlet temperature does not fall below 60 °C.
  • Run each tap and appliance in turn for at least five minutes at full temperature, and record it.

Thermal disinfection can fail where parts of the system do not get hot enough for long enough.

Why the others are wrong:

B: ten seconds is far too short a contact time.

C: 45 °C will not disinfect; it is in the growth range.

D: this is the routine outlet target, not the disinfection standard.

Memory trick:

Thermal blast: 60 at the tap for 5.

Find it in the book

HSE HSG274 Part 2, page 88

Reg HSE HSG274 Part 2, paragraph 2.133

Want 194 more CITB Plumbing (JIB) questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other CITB Plumbing (JIB) topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (HSE). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic