CITB Plumbing (JIB): Core: working environment and legal duties practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

16 of our 200 CITB HS&E Specialist Test: Plumbing (JIB) (CITB-SPEC-PLUM) questions are on core: working environment and legal duties, about 8% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. A plumber breaks his wrist falling from steps at work. Under RIDDOR, is this a specified injury?

Show answer

Answer: B. Yes, a fracture other than to fingers, thumbs or toes

  • Specified injuries include a fracture, other than to fingers, thumbs and toes.
  • Others include amputations, serious burns, loss of sight and unconsciousness from head injury or asphyxia.

The employer, or person in control of the premises, makes the report.

Why the others are wrong:

A: any fracture other than fingers, thumbs and toes is specified.

C: RIDDOR does not depend on whether the site is notifiable.

D: a specified injury is reportable whatever the time off.

Memory trick:

Broken wrist yes, broken finger no.

Find it in the book

HSE INDG453 (rev1, 2013), page 2

Reg RIDDOR 2013, regulation 4 (HSE INDG453)

Q2. A member of the public is hit by a falling fitting from your work and taken from the scene to hospital for treatment. Is it reportable?

Show answer

Answer: B. Yes, as they were taken to hospital for treatment

  • Work-related accidents to members of the public must be reported if they are injured and taken from the scene to hospital for treatment.
  • There is no need to report people taken to hospital purely as a precaution with no apparent injury.

You do not need to find out what treatment they actually received.

Why the others are wrong:

A: accidents to members of the public are covered.

C: the seven-day test applies to workers.

D: being taken from the scene to hospital for treatment is enough.

Memory trick:

Public hurt and taken to hospital: report.

Find it in the book

HSE INDG453 (rev1, 2013), page 3

Reg RIDDOR 2013 (HSE INDG453), injuries to non-workers

Q3. You are the only contractor on a small commercial job. What must you do before setting up the site?

Show answer

Answer: D. Draw up a construction phase plan for the job

  • If there is only one contractor, the contractor must draw up a construction phase plan, or arrange for one.
  • This must be done as soon as is practicable prior to setting up a construction site.

Every project needs a construction phase plan, sized to the risks.

Why the others are wrong:

A: notification is a client duty and only for notifiable projects.

B: appointing a principal designer is a client duty.

C: the file is a principal designer duty.

Memory trick:

Only contractor? You write the plan.

Find it in the book

HSE L153 (CDM 2015), page 43

Reg CDM 2015, regulation 15(5)

Q4. On a plumbing job, which of these is a reportable dangerous occurrence?

Show answer

Answer: A. A tipper lorry body touching an overhead power line

  • Dangerous occurrences are specified near-miss events with the potential to cause harm.
  • Examples include plant or equipment coming into contact with overhead power lines and failure of lifting equipment.

Explosions or fires stopping work for more than 24 hours are also reportable.

Why the others are wrong:

B: this is not a listed dangerous occurrence.

C: this has no safety significance under RIDDOR.

D: a near miss with no injury is not on the dangerous occurrence list.

Memory trick:

Plant touches power line: report it.

Find it in the book

HSE INDG453 (rev1, 2013), page 3

Reg RIDDOR 2013 (HSE INDG453), dangerous occurrences

Q5. You start on a site where the principal contractor has not given you an induction. Who must provide one?

Show answer

Answer: A. The contractor you work for

  • A contractor must give each worker under their control appropriate supervision, instructions and information.
  • This must include a suitable site induction, where not already provided by the principal contractor.

It must also cover what to do in serious and imminent danger.

Why the others are wrong:

B: a suitable site induction is required information.

C: the duty in regulation 15 is on the contractor.

D: inspectors enforce the law; they do not give site inductions.

Memory trick:

No induction from the PC? Your contractor gives it.

Find it in the book

HSE L153 (CDM 2015), page 44

Reg CDM 2015, regulation 15(9)(a)

Q6. Under CDM 2015, what must washing facilities next to site toilets include?

Show answer

Answer: A. Running hot and cold, or warm, water with soap and towels

  • Washing facilities must be in the immediate vicinity of every sanitary convenience.
  • They must include clean hot and cold, or warm, water (running where reasonably practicable), soap and towels or other drying.

Showers are needed if the work or health reasons require them.

Why the others are wrong:

B: the supply must be hot and cold, or warm.

C: wipes are not washing facilities.

D: it must be running water so far as reasonably practicable.

Memory trick:

Toilet, then warm water, soap and towel.

Find it in the book

HSE L153 (CDM 2015), page 63

Reg CDM 2015, Schedule 2, paragraph 2

Want 194 more CITB Plumbing (JIB) questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other CITB Plumbing (JIB) topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (HSE). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic