CITB Demolition: Plant, services, hazardous materials and dust practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

30 of our 150 CITB HS&E Specialist Test: Demolition (CITB-SPEC-DEM) questions are on plant, services, hazardous materials and dust, about 20% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. Weathered asbestos cement roof sheets will be pulled down by machine and broken up. How is this work normally classed?

Show answer

Answer: B. Notifiable non-licensed work (NNLW)

  • Removing AC sheets that will be substantially broken up, eg dropping an AC roof or remote mechanical demolition, is normally NNLW.
  • Removing weathered sheets whole can fall within the exemption.

NNLW must be notified and has health record and medical requirements.

Why the others are wrong:

A: breaking sheets up substantially removes the exemption.

C: it is still asbestos work and the fibres are released when broken.

D: weathered sheets removed whole can be exempt, but not when broken up.

Memory trick:

Whole sheets maybe exempt; smashed sheets NNLW.

Find it in the book

HSE L143 (2nd edition, 2013), pages 22 to 24

Reg Control of Asbestos Regulations 2012 (HSE L143), Table 3 and paragraph 69

Q2. What is the workplace exposure limit for respirable crystalline silica?

Show answer

Answer: B. 0.1 mg/m³, averaged over 8 hours

  • Control measures must keep exposure below the WEL for RCS.
  • The WEL is 0.1 mg/m³ respirable dust, averaged over 8 hours.

Monitoring may be needed to check the WEL is not exceeded.

Why the others are wrong:

A: 0.5 mg/m³ is five times the limit.

C: this is neither the right figure nor the right period.

D: the figure is right but the averaging period is 8 hours.

Memory trick:

Point one over eight.

Find it in the book

HSE INDG463 (2024), page 3

Reg HSE INDG463 (2024), what should your employer do

Q3. You are hand digging to expose a cable. How should the spade be used?

Show answer

Answer: C. Eased in with gentle foot pressure, not thrown or spiked

  • Use spades and shovels (curved edges preferred), eased in with gentle foot pressure.
  • They should not be thrown or spiked into the ground; use insulated tools near cables.

Horizontal digging gives better control for final exposure.

Why the others are wrong:

A: forcing the spade in can damage the cable.

B: spades must not be thrown or spiked.

D: picks should not be used in soft clay near services.

Memory trick:

Ease it, do not spear it.

Find it in the book

HSE HSG47 (3rd edition, 2014), page 25

Reg HSE HSG47 (2014), paragraph 110

Q4. Where do reversing alarms and lights sit in the hierarchy of controls for reversing vehicles?

Show answer

Answer: D. Lowest, and alone suit only low-risk situations

  • Warning systems give the lowest level of protection in the hierarchy.
  • Used as the only precaution, they are suitable only for low-risk situations.

Eliminating, reducing and segregating reversing come first.

Why the others are wrong:

A: they are the lowest level, not the highest.

B: segregating vehicles and pedestrians ranks above warnings.

C: warnings stay at the bottom whatever else is used.

Memory trick:

Beepers are the bottom rung.

Find it in the book

HSE HSG144 (2nd edition, 2009), page 18

Reg HSE HSG144 (2009), paragraph 40 and Table 3

Q5. An acetylene cylinder on a demolition site has been exposed to fire. What hazard zone do fire and rescue services maintain around it?

Show answer

Answer: A. 200 m

  • Heated acetylene can decompose and explode, even after the fire is out.
  • The fire service cools for 1 hour, monitors for 1 hour, and keeps a 200 m hazard zone.

Never move or strike a heated cylinder; do not try to fight a fire involving acetylene.

Why the others are wrong:

B: 25 m is far too small for a heated acetylene cylinder.

C: 50 m is too small.

D: 100 m is half the zone used.

Memory trick:

Hot acetylene: two hundred metres.

Find it in the book

HSE HSG168 (3rd edition, 2022), page 34

Reg HSE HSG168 (2022), paragraph 188

Q6. During demolition you find a cable that ends in a sealed pot in the ground. What should you assume?

Show answer

Answer: D. It may be live, even if a locator finds no signal

  • Pot-ended or bottle-ended cables should be treated as live and not assumed disused.
  • They can be difficult to detect with locators even when live.

If in doubt, treat services as live.

Why the others are wrong:

A: pot-ended cables must not be assumed to be abandoned.

B: there is no basis for assuming it is telecoms.

C: pot-ended cables can be hard to detect even when live.

Memory trick:

Sealed end, live friend: treat it as live.

Find it in the book

HSE HSG47 (3rd edition, 2014), page 21

Reg HSE HSG47 (2014), paragraphs 89 and 175

Want 144 more CITB Demolition questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other CITB Demolition topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (HSE). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic