Q1. A competent person inspecting an excavation is not satisfied it is safe. By when must the written report be given to the person it was carried out for?
Show answer
Answer: C. Within 24 hours of finishing the inspection
- The inspector must tell the person in control before the end of the shift.
- A written report must be provided within 24 hours of completing the inspection.
Work must not continue until the matter is put right.
Why the others are wrong:
A: 72 hours is too long.
B: seven days is too long.
D: the report must be provided within 24 hours.
Memory trick:
Tell them by shift end, write it within a day.
Find it in the book
HSE L153 (CDM 2015), page 53