CITB Demolition: Core: high-risk activities practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

12 of our 150 CITB HS&E Specialist Test: Demolition (CITB-SPEC-DEM) questions are on core: high-risk activities, about 8% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. A competent person inspecting an excavation is not satisfied it is safe. By when must the written report be given to the person it was carried out for?

Show answer

Answer: C. Within 24 hours of finishing the inspection

  • The inspector must tell the person in control before the end of the shift.
  • A written report must be provided within 24 hours of completing the inspection.

Work must not continue until the matter is put right.

Why the others are wrong:

A: 72 hours is too long.

B: seven days is too long.

D: the report must be provided within 24 hours.

Memory trick:

Tell them by shift end, write it within a day.

Find it in the book

HSE L153 (CDM 2015), page 53

Reg CDM 2015, regulation 24(1)(c)

Q2. Under the Work at Height Regulations, what is the first thing to consider?

Show answer

Answer: B. Avoiding work at height where reasonably practicable

  • First avoid work at height where reasonably practicable.
  • Then prevent falls, and finally minimise the distance and consequences of a fall.

In demolition, high-reach machines and remote methods can avoid work at height.

Why the others are wrong:

A: harnesses are personal protection, which comes later.

C: minimising falls is the third step, after avoid and prevent.

D: ladder use is a selection point, not the first step.

Memory trick:

Avoid, prevent, minimise.

Find it in the book

HSE INDG401(rev2) (2014), page 1

Reg Work at Height Regulations 2005 (HSE INDG401), simple steps

Q3. During a roof strip before demolition, which material should you treat as likely to be fragile?

Show answer

Answer: C. Non-reinforced fibre cement sheets

  • Likely fragile materials include roof lights, non-reinforced fibre cement sheets, corroded metal sheets, glass, rotted chipboard, and slates and tiles.
  • Falls through fragile roofs are a common cause of death.

Old fibre cement sheets may also contain asbestos.

Why the others are wrong:

A: a concrete roof slab is given as an example of an existing safe place.

B: a guarded mezzanine is an example of a safe existing place of work.

D: a fully boarded, guarded scaffold is a safe working platform.

Memory trick:

Cement sheet: do not step, it will not keep.

Find it in the book

HSE INDG401(rev2) (2014), page 3

Reg Work at Height Regulations 2005 (HSE INDG401), fragile surfaces

Q4. A driver wants to park a loaded dumper right at the edge of a trench. What is the main risk?

Show answer

Answer: D. The extra load can make the trench sides collapse

  • Do not park plant or store spoil close to the sides of excavations.
  • The extra loading makes the sides more likely to collapse, and loose material can fall in.

CDM 2015 requires steps to stop excavation edges being overloaded.

Why the others are wrong:

A: the weight still loads the trench edge with the engine off.

B: the main risk is collapse onto anyone in the trench.

C: the handbrake does not reduce the load on the edge.

Memory trick:

Heavy at the edge, sides on the slide.

Find it in the book

HSE HSG150 (3rd edition, 2006), page 73

Reg HSG150 (2006), paragraph 350; CDM 2015, regulation 22(3)

Q5. A scaffold platform from which someone could fall more than 2 m is in use. What is the longest interval between inspections?

Show answer

Answer: B. Seven days

  • Construction working platforms with a fall of more than 2 m must be inspected after assembly, after any event affecting stability, and at intervals not exceeding seven days.
  • A record of the inspection must be kept.

Mobile platforms moved on the same site do not need a new inspection each move.

Why the others are wrong:

A: 14 days is too long.

C: a month is too long.

D: three months is far too long.

Memory trick:

Two metres up, seven days max.

Find it in the book

HSE INDG401(rev2) (2014), page 5

Reg Work at Height Regulations 2005 (HSE INDG401), inspection of working platforms

Q6. You are planning work where an operative could be left hanging in a fall-arrest harness. What does HSE say about rescue?

Show answer

Answer: C. Plan your own rescue, not just relying on 999

  • Plan for emergencies and rescue, eg agree a set evacuation procedure.
  • Do not rely entirely on the emergency services for rescue in your plan.

Make sure workers know the emergency procedures before they start.

Why the others are wrong:

A: you must not rely entirely on the emergency services.

B: leaving someone suspended is dangerous; rescue must be planned.

D: rescue planning applies to all work at height, not just MEWPs.

Memory trick:

Your fall, your rescue plan.

Find it in the book

HSE INDG401(rev2) (2014), page 3

Reg Work at Height Regulations 2005 (HSE INDG401), planning for emergencies and rescue

Want 144 more CITB Demolition questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other CITB Demolition topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (HSE). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic