CITB Demolition: Planning demolition, surveys and the demolition plan practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

30 of our 150 CITB HS&E Specialist Test: Demolition (CITB-SPEC-DEM) questions are on planning demolition, surveys and the demolition plan, about 20% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. What is the key to developing a safe system of work for demolition?

Show answer

Answer: B. A method that keeps people as far from the risk as possible

  • The key is choosing a work method that keeps people as far away as possible from the risks.
  • The methods are best set out in a method statement, and people must be supervised to follow it.

Machine demolition from a distance is one example.

Why the others are wrong:

A: hand demolition puts people close to the risk, however experienced.

C: speed is not a control and can add risk.

D: PPE is the last line of defence, not the key to the system.

Memory trick:

Distance is the best defence.

Find it in the book

HSE HSG150 (3rd edition, 2006), page 79

Reg HSG150 (2006), paragraph 392

Q2. On a multi-contractor demolition project, who must help the client provide pre-construction information?

Show answer

Answer: C. The principal designer

  • The principal designer must help the client provide pre-construction information to designers and contractors.
  • The level of help depends on the project and the client's experience.

The principal designer also helps fill gaps, eg by commissioning surveys.

Why the others are wrong:

A: the principal contractor has no specific duty on pre-construction information.

B: the local authority is not a CDM dutyholder for this.

D: HSE enforces the law; it does not prepare project information.

Memory trick:

The PD helps the client pack the information.

Find it in the book

HSE L153 (CDM 2015), page 76

Reg CDM 2015, regulation 11(6); L153 Appendix 2 paragraph 11

Q3. Which check on a demolition contractor's safety record does HSG150 suggest the client should make?

Show answer

Answer: C. Whether it has had improvement or prohibition notices

  • Clients should find out whether the contractor has had improvement or prohibition notices or been prosecuted.
  • Also its injury, near miss and dangerous occurrence statistics and its safety adviser arrangements.

Enforcement history for firms is published on HSE's website.

Why the others are wrong:

A: start date is not a check on safety record.

B: owning plant is not one of the safety checks listed.

D: distance from site says nothing about safety.

Memory trick:

Check the notices before the contract.

Find it in the book

HSE HSG150 (3rd edition, 2006), page 79

Reg HSG150 (2006), paragraph 389

Q4. What must a construction phase plan for a demolition project record?

Show answer

Answer: B. The arrangements, the site rules and any Schedule 3 measures

  • The plan must record the health and safety arrangements, the site rules and, where relevant, specific measures for Schedule 3 work.
  • It should not include generic risk assessments, decision records or detailed method statements.

It should be simple, relevant and proportionate.

Why the others are wrong:

A: generic risk assessments should not be included as they get in the way.

C: detailed method statements should not be included in the plan.

D: records of decision-making should not be included.

Memory trick:

Arrangements, rules, Schedule 3: keep the rest out.

Find it in the book

HSE L153 (CDM 2015), page 77

Reg CDM 2015, regulation 12(2); L153 Appendix 3 paragraphs 2 and 4

Q5. The client wants the street frontage kept while the building behind is demolished. Whose expertise must be used to design the retention scheme?

Show answer

Answer: A. A structural engineer

  • A structural engineer must be used in the design of a façade retention scheme.
  • Also where there is doubt about stability, the demolition method or the building's capacity to take loads.

Façade retention leaves a tall wall standing on its own, so it needs proper design.

Why the others are wrong:

B: plant operators carry out the work; they do not design retention schemes.

C: asbestos surveyors identify asbestos, not structural schemes.

D: first aiders have no role in structural design.

Memory trick:

Keep the face, call the engineer.

Find it in the book

HSE HSG150 (3rd edition, 2006), page 78

Reg HSG150 (2006), paragraph 386

Q6. On a demolition project with more than one contractor, who draws up the construction phase plan?

Show answer

Answer: B. The principal contractor

  • For projects with more than one contractor, the principal contractor prepares, reviews and revises the plan.
  • It must be drawn up before the construction site is set up.

The client must make sure this happens.

Why the others are wrong:

A: the principal designer helps by providing information but does not draw up the plan.

C: the client must ensure a plan is drawn up but does not write it.

D: contractors follow the relevant parts; the principal contractor leads.

Memory trick:

PC writes the CPP.

Find it in the book

HSE L153 (CDM 2015), pages 78 to 79

Reg CDM 2015, regulation 12(1); L153 Appendix 3 paragraph 11

Want 144 more CITB Demolition questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other CITB Demolition topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (HSE). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic