QELTK3/007: Fault diagnosis principles and safe working practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

54 of our 120 Fault Diagnosis and Rectification (QELTK3-007) questions are on fault diagnosis principles and safe working, about 45% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. What is the first principle of a permit-to-work system?

Show answer

Answer: C. Eliminate the hazard if possible so no permit is needed

  • The first principle: wherever possible eliminate the hazard so a permit is not needed.
  • If it cannot be eliminated, the permit controls the work.

The best safety control is removing the danger altogether.

Why the others are wrong:

A: permits are for high-risk work, and removing the hazard comes first.

B: permits are issued by an authorised person, not self-issued.

D: it is a safety control, not a timesheet.

Memory trick:

Best permit is the one you never need.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 324

Reg Permit to work

Q2. How does flameproof (Ex 'd') equipment stop an internal explosion igniting the surrounding gas?

Show answer

Answer: D. Its strong enclosure contains the blast and wide flanges cool the flame

  • A flameproof enclosure withstands an internal explosion.
  • Wide flanges, firmly bolted, cool the flame as it passes across, so it cannot ignite the outside atmosphere.

It contains the bang rather than preventing it.

Why the others are wrong:

A: flameproof enclosures assume gas can enter; they contain the explosion instead.

B: that describes pressurisation, not flameproof construction.

C: that is closer to intrinsic safety, not flameproof design.

Memory trick:

Flameproof: let it bang inside, keep the flame inside.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 326

Reg Flameproof equipment

Q3. Part way through a fault-finding job you realise the problem is beyond your training and experience. What should you do?

Show answer

Answer: D. Tell the person who ordered the work straight away

  • Recognise your own limits and tell the person ordering the work immediately.
  • Clients respect honesty more than a failed attempt.

Seeking help is part of competent fault diagnosis.

Why the others are wrong:

A: attempting work beyond your competence can create bigger problems and danger.

B: the client must be told; walking away without explanation is poor practice.

C: guesswork wastes time and money and may add new faults.

Memory trick:

Know your limits, say so early.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 340

Reg Competence

Q4. An explosive gas-air mixture is not expected in normal operation and, if it occurs, lasts about 6 hours in a year. Which zone is this?

Show answer

Answer: B. Zone 2

  • Zone 2: not likely in normal operation and, if it occurs, only briefly, usually fewer than 10 hours per year.

This is the least hazardous classified zone.

Why the others are wrong:

A: zone 0 is continuous or long-term presence.

C: zone 1 is where the mixture is likely in normal operation.

D: there are only zones 0, 1 and 2 for gas.

The maths

Step 1: 6 h is far below 1,000 h, so not zone 0 or zone 1.
Step 2: 6 h is fewer than 10 h and not expected in normal operation.
Step 3: zone 2.

Memory trick:

Under 10 hours a year: zone 2.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 326

Reg Hazardous area zones

Q5. After testing a distribution circuit dead, an electrician re-checks the voltage indicator on the proving unit and it no longer lights. What is the correct conclusion?

Show answer

Answer: D. Treat it as live and repeat with a working indicator

  • GS 38 recommends proving the indicator before and after use because it is not fail-safe.
  • A failed after-check means the instrument could have been faulty during the test.

The circuit must be treated as live until it is re-tested with an instrument that is proved working.

Why the others are wrong:

A: PPE is not a substitute for a valid proof of dead; the isolation has not been confirmed.

B: the indicator may have failed before the dead test, so that result proves nothing.

C: there is no evidence the proving unit failed; assuming so risks working on a live circuit.

Memory trick:

No proof after, no proof at all.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 338

Reg GS 38

Q6. You need to measure prospective fault current at a sub-main where the protection upstream is in doubt. What does GN3 say about where to connect the instrument?

Show answer

Answer: D. Downstream of a device rated for the fault current

  • GN3 recommends determining PFC by other means where possible.
  • Where measurement is necessary it should be made downstream of a protective device rated for the anticipated fault current.
  • Fused leads alone are not enough; fit a temporary device if needed.

This follows the hazards noted in Appendix 14 and HSR25.

Why the others are wrong:

A: setting the range does not protect against the energy of a fault at that point.

B: GN3 says fused test leads alone are not considered suitable protection.

C: this places the instrument with the least protection, which is the opposite of the advice.

Memory trick:

Measure behind a guard that can take the hit.

Find it in the book

IET Guidance Note 3 (2022 edition), page 89

Reg Appendix 14