PAS 2035/2030 Retrofit: Whole-dwelling design, ventilation and moisture risk practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

24 of our 160 PAS 2035/2030 Retrofit Standards (Warm Homes) (PAS-RETROFIT) questions are on whole-dwelling design, ventilation and moisture risk, about 15% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. How must a new continuous mechanical ventilation system's airflow be controlled under PAS 2035:2023?

Show answer

Answer: B. Automatically, responding to a sensed parameter such as humidity

  • C.3.6: the whole-dwelling rate is controlled automatically to keep good IAQ and avoid wasting energy.
  • Airflow must not be controlled solely by light switches or manual switches; controls respond to a local control parameter (e.g. RH, CO2, presence).

This is often called demand control.

Why the others are wrong:

A: airflow must not be controlled solely by light or manual switches.

C: the rate must vary automatically between background and high.

D: manual switching alone does not meet C.3.6.

Memory trick:

Let the sensor decide.

Find it in the book

BSI PAS 2035:2023, page 39

Reg PAS 2035:2023, Annex C, C.3.6

Q2. Which of these is classed as a wet room in Annex C of PAS 2035:2023?

Show answer

Answer: D. A utility room

  • C.2.2 NOTE 1: wet rooms include kitchens, bathrooms, shower rooms, utility rooms and WCs without openable windows.
  • Continuous MEV and MVHR extract moist stale air from all wet rooms.

Wet rooms are where most moisture is produced.

Why the others are wrong:

A: dining rooms are habitable rooms, not wet rooms.

B: bedrooms receive supply air, not extract.

C: halls are not listed as wet rooms.

Memory trick:

Wash, cook, launder: wet room.

Find it in the book

BSI PAS 2035:2023, page 38

Reg PAS 2035:2023, Annex C, C.2.2 NOTE 1

Q3. Who must the retrofit design specify to install a new ventilation system?

Show answer

Answer: A. Scheme-registered fitters approved by the maker

  • C.3.12: the design specifies installation by operatives registered with a relevant competent persons scheme and approved by the manufacturer or supplier.
  • C.3.13: the system is inspected, and new mechanical systems are tested and commissioned.

Badly installed ventilation is a common cause of mould after retrofit.

Why the others are wrong:

B: occupants are not installers of ventilation systems.

C: a labourer's card does not meet C.3.12.

D: the assessor does not install the system.

Memory trick:

Ventilation by registered, approved fitters.

Find it in the book

BSI PAS 2035:2023, page 40

Reg PAS 2035:2023, Annex C, C.3.12

Q4. A client can only afford to insulate the walls now and the roof later. What must the stage-by-stage design include?

Show answer

Answer: D. Cold surface risk controls, without blocking later work

  • 8.2.17: stage-by-stage insulation includes provisions to mitigate cold surface risks, such as heating and continuous ventilation.
  • 8.2.18: treated elements must not inhibit later insulation of other elements, with suitable junction details.

The medium-term plan prioritises adjacent elements next.

Why the others are wrong:

A: PAS 2035 requires design mitigation, not a waiver.

B: elements can be treated; junctions need suitable details.

C: PAS 2035 sets no fixed time for the next stage.

Memory trick:

Stage it, but don't block the next stage.

Find it in the book

BSI PAS 2035:2023, page 18

Reg PAS 2035:2023, clause 8.2.17 and 8.2.18

Q5. According to BRE research quoted in PAS 2035:2023, what is the average air permeability of UK dwellings with fans and vents sealed?

Show answer

Answer: A. 11.5 ach at 50 Pa

  • C.1: BRE research gives an average of 11.5 ach at 50 Pa with fans and background vents sealed.
  • Infiltration and leakage provide about three-quarters of the ventilation most homes rely on.

Tightening the envelope removes most of that accidental ventilation.

Why the others are wrong:

B: 5 is the air permeability figure used in Annex C thresholds, in different units.

C: this is far tighter than the average UK home.

D: this is far leakier than the average quoted.

Memory trick:

Eleven and a half, leaky by habit.

Find it in the book

BSI PAS 2035:2023, page 37

Reg PAS 2035:2023, Annex C, C.1

Q6. Which document must the Retrofit Designer use to assess overheating risk when designing measures to inhibit overheating?

Show answer

Answer: C. CIBSE TM59, the overheating risk methodology for homes

  • Clause 8.2.31: the design includes measures to inhibit overheating over the installed life of the EEMs.
  • Overheating risk is assessed using CIBSE TM59; UKCIP tools and the Guide to low energy shading are also used.

Sealing up a home can make summer overheating worse.

Why the others are wrong:

A: BS 5250 covers moisture management, not overheating.

B: IP1/06 is used for temperature factors at junctions.

D: TM23 covers airtightness testing, not overheating.

Memory trick:

Fifty-nine for heat, twenty-three for leaks.

Find it in the book

BSI PAS 2035:2023, page 19

Reg PAS 2035:2023, clause 8.2.31 a)

Want 154 more PAS 2035/2030 Retrofit questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other PAS 2035/2030 Retrofit topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (GOV.UK). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic