PAS 2035/2030 Retrofit: Measure-specific requirements (PAS 2030 annexes) practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

24 of our 160 PAS 2035/2030 Retrofit Standards (Warm Homes) (PAS-RETROFIT) questions are on measure-specific requirements (pas 2030 annexes), about 15% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. Draught strips are being fitted to wooden hinged doors and sliding sash windows in a house not built with them. Which standards apply?

Show answer

Answer: D. Products to BS 7386 installed in line with BS 7880

  • B2-l1: for retrofitted draught strips on wooden doors and windows, steel hinged windows and loft hatches, installers use products meeting BS 7386 working in accordance with BS 7880.
  • Checks include asbestos, rot and combustion appliance ventilation.

Draught-proofing must not starve fuel-burning appliances of air.

Why the others are wrong:

A: BS 7593 is water treatment and BS 5970 is pipework insulation.

B: BS 6262-4 is glazing safety and BS 7913 is historic buildings.

C: BS 5250 is moisture and BS 8000-7 is glazing workmanship.

Memory trick:

Strip to 7386, fit to 7880.

Find it in the book

BSI PAS 2030:2023, page 31

Reg PAS 2030:2023, Annex B.2, Table B.2 (B2-l1)

Q2. An installer finds recessed downlighters in the ceiling below a loft being insulated. What must happen?

Show answer

Answer: C. They are not covered and are boxed so air can circulate

  • B9-l1: recessed downlighters shall not be covered by insulation because of the risk of overheating.
  • They are boxed to permit adequate ventilation around them; wiring that must not be covered is relocated above the insulation.

Heat trapped around a fitting is a fire risk.

Why the others are wrong:

A: PAS 2030 gives no LED exception to the rule.

B: downlighters must not be covered because of the overheating risk.

D: the requirement is to box them, not remove them.

Memory trick:

Box the light, don't bury it.

Find it in the book

BSI PAS 2030:2023, page 57

Reg PAS 2030:2023, Annex B.9, Table B.9 (B9-l1)

Q3. At handover of new electric storage heaters, what must the explanation of user controls include?

Show answer

Answer: A. An explanation of tariffs

  • D1-l7: the installer demonstrates how to set user controls for maximum efficiency, including an explanation of tariffs.
  • They also explain what should not be adjusted by the user and what to do in an emergency.

Storage heaters only save money on the right tariff.

Why the others are wrong:

B: safety devices must not be bypassed.

C: users are told which parts not to adjust, not how to rewire.

D: servicing is not a user handover item.

Memory trick:

Storage heat needs tariff talk.

Find it in the book

BSI PAS 2030:2023, page 99

Reg PAS 2030:2023, Annex D.1, Table D.1 (D1-l7)

Q4. External wall insulation is proposed on a cavity wall with an empty, unfilled cavity. What does PAS 2030:2023 say?

Show answer

Answer: C. Do not install unless cavities are sealed to the design details

  • B4-l1: due to the high risk of thermal bypass, EWI is not installed on cavity walls with unfilled cavities (or with CWI removed and not replaced).
  • The exception is where cavities are sealed to specifications and details from the Retrofit Designer.

Cold air moving in the cavity bypasses the insulation outside it.

Why the others are wrong:

A: the finish does not deal with air movement in the cavity.

B: any sealing must follow the Retrofit Designer's specification.

D: an open cavity behind EWI creates a high risk of thermal bypass.

Memory trick:

Open cavity behind EWI equals bypass.

Find it in the book

BSI PAS 2030:2023, page 35

Reg PAS 2030:2023, Annex B.4, Table B.4 (B4-l1)

Q5. A room-in-roof job leaves the dwarf walls uninsulated. When is this partial treatment acceptable under PAS 2030:2023?

Show answer

Answer: B. Where health and safety suffers or over 5% of floor space is lost

  • B.12.1 NOTE: room-in-roof insulation covers all heat-loss elements (flat ceiling, slopes, dwarf walls, gables).
  • Partial insulation is not compliant, except where health and safety is compromised or more than 5% of the room floor space would be lost.

Untreated elements leave cold spots and condensation risk.

Why the others are wrong:

A: cost is not listed as an exception.

C: the threshold in the annex is 5%, not 10%.

D: client preference is not one of the exceptions.

Memory trick:

All of the room, unless five per cent goes.

Find it in the book

BSI PAS 2030:2023, page 66

Reg PAS 2030:2023, Annex B.12, clause B.12.1 NOTE

Q6. Which British Standard must be followed, in addition to the relevant insulation annexes, when insulating an existing residential park home?

Show answer

Answer: A. BS 3632:2015

  • B13-l1: park home insulation follows the relevant measure annexes and complies with BS 3632:2015, the residential park home specification.
  • Ventilation to spaces not in the project is maintained to BS 3632:2015, 4.10.

Park homes have their own construction standard.

Why the others are wrong:

B: BS 7913 covers historic buildings.

C: BS 8000-0 covers general workmanship.

D: BS 5250 is the moisture code, not the park home specification.

Memory trick:

Park homes: thirty-six thirty-two.

Find it in the book

BSI PAS 2030:2023, page 68

Reg PAS 2030:2023, Annex B.13, Table B.13 (B13-l1)

Want 154 more PAS 2035/2030 Retrofit questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other PAS 2035/2030 Retrofit topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (GOV.UK). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic