PAS 2035/2030 Retrofit: Handover, monitoring, evaluation and lodgement practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

20 of our 160 PAS 2035/2030 Retrofit Standards (Warm Homes) (PAS-RETROFIT) questions are on handover, monitoring, evaluation and lodgement, about 13% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. What must handover information explain about installed ventilation?

Show answer

Answer: A. Why it must not be switched off

  • 11.1.2 g): handover covers the importance of ventilation for indoor air quality and controlling summer overheating.
  • It also covers the implications of switching off or disabling any installed ventilation system.

Occupants often switch off fans because of noise or cost.

Why the others are wrong:

B: this is not a handover requirement.

C: sealing vents undermines ventilation.

D: this is not the stated handover item.

Memory trick:

Explain why it must stay on.

Find it in the book

BSI PAS 2035:2023, page 24

Reg PAS 2035:2023, clause 11.1.2 g)

Q2. By when must basic evaluation of a retrofit project be completed and reported?

Show answer

Answer: C. Within three months after handover

  • Clause 13.4.3: basic evaluation is completed and reported within three months after handover.
  • It is the minimum level of evaluation for every completed project (13.3.1).

Early feedback catches problems while they are fresh.

Why the others are wrong:

A: one month is shorter than the period set.

B: six months is longer than the period set.

D: twelve months is the historic energy data period, not this deadline.

Memory trick:

Basic evaluation in a quarter.

Find it in the book

BSI PAS 2035:2023, page 28

Reg PAS 2035:2023, clause 13.4.3

Q3. A stage of the retrofit set out in the improvement plan has been completed. What must the Retrofit Coordinator give the client?

Show answer

Answer: D. A new or updated medium-term improvement plan

  • 11.1.5: whenever any stage of the retrofit is completed, the coordinator provides an updated medium-term improvement plan reflecting the works.
  • The plan guides the next stages and records what is done.

A staged retrofit needs a living plan.

Why the others are wrong:

A: certificates come from the installer or building control.

B: invoicing is not a PAS 2035 handover requirement.

C: a new assessment is not required at each stage.

Memory trick:

Stage done, plan updated.

Find it in the book

BSI PAS 2035:2023, page 24

Reg PAS 2035:2023, clause 11.1.5

Q4. After handover, what must the Retrofit Coordinator recommend to the client?

Show answer

Answer: A. That a new or updated EPC is prepared for the dwelling

  • Clause 11.1.4: after handover the coordinator recommends a new or updated EPC.
  • If accepted, the coordinator arranges it with a domestic energy assessor.

An EPC may be legally needed if the home is sold or re-let.

Why the others are wrong:

B: finance advice is not part of this requirement.

C: PAS 2035 does not require this recommendation.

D: this is not the post-handover recommendation in clause 11.

Memory trick:

Handed over? Update the EPC.

Find it in the book

BSI PAS 2035:2023, page 24

Reg PAS 2035:2023, clause 11.1.4

Q5. The tenants of a retrofitted rented house refuse to receive the handover information. What does PAS 2035:2023 allow?

Show answer

Answer: D. Handing over to the client only, usually the landlord

  • 11.2.1: handover is to the occupants; where they are not the clients, landlords and clients are included.
  • NOTE: if tenants refuse, it is sufficient to hand over only to the client, usually the landlord or housing association.

The aim is that someone responsible understands the measures.

Why the others are wrong:

A: refusal by tenants does not make the project incomplete.

B: PAS 2035 accepts handover to the client alone in this case.

C: the client still receives a proper handover.

Memory trick:

Tenants say no? Landlord gets the pack.

Find it in the book

BSI PAS 2035:2023, page 24

Reg PAS 2035:2023, clause 11.2.1 and NOTE

Q6. Who is responsible for delivering retrofit advice at handover?

Show answer

Answer: B. The Main Contractor or installer, under coordinator oversight

  • 12.1.8 NOTE 1: handover advice is the responsibility of the Main Contractor or Retrofit Installer, still subject to oversight by the Retrofit Coordinator.
  • It covers installed EEMs, controls, ventilation, maintenance and guarantees.

All retrofit advice is overseen by the coordinator (12.1.1).

Why the others are wrong:

A: suppliers are not the named party for handover advice.

C: evaluation follows handover; it is not the handover advice.

D: the assessor's advice role is earlier in the process.

Memory trick:

Installer explains, coordinator oversees.

Find it in the book

BSI PAS 2035:2023, page 26

Reg PAS 2035:2023, clause 12.1.8 NOTE 1

Want 154 more PAS 2035/2030 Retrofit questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other PAS 2035/2030 Retrofit topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (GOV.UK). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic