Q1. The Retrofit Coordinator cannot visit site in person. For which measure can they NOT rely on third-party digital evidence?

Show answer

Answer: B. External wall insulation

  • 9.2: if an in-person visit is not possible, digital evidence from a third party is allowed only for listed measures (e.g. loft, cavity wall, boiler replacement, solar PV).
  • Any EEM not listed, such as external wall insulation, needs an in-person inspection; so does a listed measure that penetrates another fabric EEM.

Complex fabric work needs eyes on site.

Why the others are wrong:

A: party cavity wall insulation is on the list allowing digital evidence.

C: boiler replacement is on the list allowing digital evidence.

D: loft insulation is on the list allowing digital evidence.

Memory trick:

EWI needs boots on the ground.

Find it in the book

BSI PAS 2035:2023, page 22

Reg PAS 2035:2023, clause 9.2

Q2. During a pre-installation building inspection the inspector finds bats roosting in the loft. What must be done?

Show answer

Answer: D. Record it and tell the installer and the Retrofit Coordinator

  • Clause 7.2.7: where species or plants that could be specially protected are found, the inspector includes it in the inspection record.
  • The presence is made known to the Retrofit Installer and the Retrofit Coordinator.

Examples given include bats, birds, butterflies and dormice.

Why the others are wrong:

A: the record and the installer and coordinator must be informed.

B: the presence of protected species must be recorded and reported first.

C: species that may be protected must not simply be removed.

Memory trick:

Bats in the loft? Write it down, pass it on.

Find it in the book

BSI PAS 2030:2023, page 16

Reg PAS 2030:2023, clause 7.2.7

Q3. An installer is contracted on a design and build basis. What does PAS 2030:2023 require in the contract documents?

Show answer

Answer: A. The design and installer roles are clearly split

  • 7.9.2: on a design and build basis, the roles of Retrofit Designer and Retrofit Installer are clearly defined and distinguished in the contract.
  • This permits claims against either or both if the installation is defective.

Clear roles mean clear liability.

Why the others are wrong:

B: this is not the requirement in 7.9.2.

C: the coordinator role is separate and must still be appointed.

D: the aim is to allow claims, not prevent them.

Memory trick:

Design and build? Separate the hats on paper.

Find it in the book

BSI PAS 2030:2023, page 17

Reg PAS 2030:2023, clause 7.9.2

Q4. Under PAS 2030:2023, when may the Retrofit Installer start installing measures?

Show answer

Answer: B. Once a site-specific PAS 2035 design is obtained and validated

  • Clause 5.1: for each installation the installer obtains a location-specific retrofit design conforming to PAS 2035 for the complete package.
  • Installation shall not commence until the design has been obtained and validated.

No design, no drill.

Why the others are wrong:

A: a contract alone is not enough without a validated design.

C: an EPC is not the trigger in PAS 2030 clause 5.1.

D: material delivery does not satisfy the design requirement.

Memory trick:

Get it, check it, then fit it.

Find it in the book

BSI PAS 2030:2023, page 9

Reg PAS 2030:2023, clause 5.1

Q5. An installer asks the Retrofit Coordinator for a toolbox talk on an unfamiliar product, and the coordinator refuses. What must the installer do?

Show answer

Answer: A. Ask the coordinator to justify why no briefing is given

  • Clause 6.5.2: briefings shall always be requested in set cases, including new or unusual products the installer is not familiar with.
  • If a request is refused, the installer asks the Retrofit Coordinator to justify why a briefing need not or cannot be given.

Toolbox talks explain the design intent and installation sequence.

Why the others are wrong:

B: the first step is to ask for a justification.

C: the briefing on design intent comes from the coordinator.

D: PAS 2030 requires the installer to seek a justification.

Memory trick:

Refused a briefing? Ask why.

Find it in the book

BSI PAS 2030:2023, page 13

Reg PAS 2030:2023, clause 6.5.2

Q6. What must a Retrofit Installer's process continuity plan ensure?

Show answer

Answer: D. Unfinished jobs pass to another installer to complete

  • Clause 7.5: if unforeseen circumstances stop the installer finishing, all uncompleted installations are transferred to another Retrofit Installer and completed in accordance with the design and PAS 2030.
  • Where the installer is a subcontractor, the main contractor confirms a plan is in place.

Clients should not be left with half a retrofit.

Why the others are wrong:

A: the plan transfers work to another installer.

B: unfinished work must be completed, not signed off.

C: the plan is about completing work, not refunds.

Memory trick:

If you stop, someone else finishes.

Find it in the book

BSI PAS 2030:2023, page 16

Reg PAS 2030:2023, clause 7.5

Want 154 more PAS 2035/2030 Retrofit questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other PAS 2035/2030 Retrofit topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (GOV.UK). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic