Part L Energy Efficiency: Existing dwellings, commissioning and handover practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

36 of our 120 Part L Energy Efficiency (Domestic Heating) (PART-L-ENERGY) questions are on existing dwellings, commissioning and handover, about 30% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. A replacement window is being fitted to an existing house. Which performance meets AD L's limiting standard?

Show answer

Answer: C. U-value of 1.4 W/m²K or Window Energy Rating Band B

  • Windows in existing dwellings should achieve 1.4 W/m²K or a Window Energy Rating of Band B minimum (2026 Table 3.2; 2021 Table 4.2).
  • Units should also be draught-proofed, with insulated cavity closers where appropriate.

A WER from a quality-assured scheme can be accepted as evidence.

Why the others are wrong:

A: 1.6 W/m²K is the window limit for new dwellings, and Band C falls short of the Band B minimum.

B: 2.2 W/m²K is the rooflight limit, and Band D falls short of the Band B minimum.

D: Band C is the Doorset Energy Rating minimum for doors over 60% glazed, not windows.

Memory trick:

Replacement window: 1.4 or Band B.

Find it in the book

Approved Document L Vol 1 2021 (incl. 2023), page 25; 2026 edition, page 26

Reg Approved Document L Vol 1, 2021 (incl. 2023 amendments) Table 4.2; 2026 edition Table 3.2

Q2. Where an upgraded thermal element cannot reach the improved U-value, what U-value should it generally not exceed?

Show answer

Answer: B. 0.7 W/m²K

  • Generally, an upgraded thermal element should not have a U-value greater than 0.7 W/m²K (2026 para 3.14; 2021 para 4.13).
  • A higher value may be accepted where needed to comply with Part C on condensation.

This is the fallback when the improved value is not feasible.

Why the others are wrong:

A: 0.18 is the new wall limit in existing dwellings.

C: 0.35 is the roof threshold value.

D: 1.4 is the replacement window limit.

Memory trick:

Upgraded but limited? Still no worse than 0.7.

Find it in the book

Approved Document L Vol 1 2021 (incl. 2023), page 26; 2026 edition, page 27

Reg Approved Document L Vol 1, 2021 (incl. 2023 amendments) 4.13; 2026 edition 3.14

Q3. What should the notice of completion of commissioning confirm to building control?

Show answer

Answer: B. The commissioning plan was followed and results reasonably match the design

  • The notice confirms the commissioning plan was followed, systems were inspected in an appropriate sequence to a reasonable standard, and test results are reasonably in accordance with the design (2026 para 7.4; 2021 para 8.4).
  • It goes to the relevant building control body.

Without it, a completion certificate may be held back.

Why the others are wrong:

A: this is not part of the notice.

C: the notice is about commissioning, not maintenance.

D: payment is not part of the notice.

Memory trick:

Plan followed, inspected, tested.

Find it in the book

Approved Document L Vol 1 2021 (incl. 2023), page 55; 2026 edition, page 64

Reg Approved Document L Vol 1, 2021 (incl. 2023 amendments) 8.4; 2026 edition 7.4

Q4. A barn is converted into a dwelling (a material change of use). An existing window separating heated space from outside has a U-value of 3.5 W/m²K. What should happen?

Show answer

Answer: C. Replace it to the new window standard, as it exceeds 3.30 W/m²K

  • On a material change of use or change to energy status, existing windows, roof windows and doors worse than 3.30 W/m²K that separate heated and unheated space or outside should be replaced (para 11.7(b), same in both editions).
  • The rooflight trigger is 3.80 W/m²K.

Replacements must meet the new elements table.

Why the others are wrong:

A: 3.80 is the rooflight figure; windows use 3.30.

B: AD L uses 3.30 W/m²K as the trigger for windows.

D: windows worse than 3.30 W/m²K should be replaced.

Memory trick:

Windows over 3.3 in a conversion: replace.

Find it in the book

Approved Document L Vol 1 2021 (incl. 2023), page 69; 2026 edition, page 86

Reg Approved Document L Vol 1, 2021 (incl. 2023 amendments) 11.7(b); 2026 edition 11.7(b)

Q5. Reaching the improved U-value on a renovated wall is technically possible but would not pay back in time. AD L says to upgrade to the lowest U-value that is feasible and achieves a simple payback of no more than:

Show answer

Answer: A. 15 years

  • If the improved value is not feasible or would not achieve a simple payback of 15 years or less, upgrade to the lowest U-value that is feasible and pays back within 15 years (2026 para 3.14; 2021 para 4.13).
  • An upgraded element should generally not be worse than 0.7 W/m²K.

Part C condensation risk can justify a lesser standard.

Why the others are wrong:

B: 7 years is the payback used for thermostatic room controls.

C: AD L uses 15 years, not 25.

D: AD L uses 15 years for this test.

Memory trick:

Fabric payback test: 15 years.

Find it in the book

Approved Document L Vol 1 2021 (incl. 2023), page 26; 2026 edition, page 27

Reg Approved Document L Vol 1, 2021 (incl. 2023 amendments) 4.13; 2026 edition 3.14

Q6. What may building control do until it receives the notice of completion of commissioning?

Show answer

Answer: D. Decide not to issue a completion or final certificate

  • 2026 para 7.7 (2021: 8.7): until the notice of completion of commissioning is received, the building control body may decide not to give a completion or final certificate.
  • The notice confirms the commissioning plan was followed and test results meet the design.

A registered competent person may give the notice.

Why the others are wrong:

A: the notice is required, and the certificate may be withheld.

B: AD L does not give this power.

C: AD L does not describe daily fines.

Memory trick:

No commissioning notice, no completion certificate.

Find it in the book

Approved Document L Vol 1 2021 (incl. 2023), page 55; 2026 edition, page 65

Reg Approved Document L Vol 1, 2021 (incl. 2023 amendments) 8.7; 2026 edition 7.7

Want 114 more Part L Energy Efficiency questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other Part L Energy Efficiency topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (GOV.UK). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.