MCS Heat Pumps and BUS: MCS certification: operating requirements, customer commitment, contracts and quotes practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

28 of our 160 MCS Heat Pump Installer and Boiler Upgrade Scheme (MCS-HP-BUS) questions are on mcs certification: operating requirements, customer commitment, contracts and quotes, about 18% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. Under the MCS Installer Operating Requirements 2.0 (redeveloped MCS scheme), how soon after commissioning must you raise the MCS certificate?

Show answer

Answer: C. Within 30 calendar days

  • Raise an MCS certificate within 30 calendar days of commissioning.
  • The certificate is your declaration that the installation meets scheme requirements.

You must also record the Technical Supervisor for each installation.

Why the others are wrong:

A: 6 months is the GSHP voucher validity, not the certificate deadline.

B: 10 working days is not the MCS certificate deadline.

D: 120 days is the BUS application window after commissioning.

Memory trick:

Thirty days to certify.

Find it in the book

MCS Installer Operating Requirements 2.0 (2026), page 13

Reg MCS Installer Operating Requirements 2.0 (2026), clause 4.10

Q2. Which item must a record of a customer complaint include as a minimum under Appendix A of the IOR 2.0?

Show answer

Answer: C. The root cause of the complaint

  • Complaint records include the complainant and installation, nature, date received, date and outcome of resolution, the root cause, the action taken and action to prevent recurrence.
  • A simple secure log or spreadsheet is acceptable.

The MCS Principles for Good Complaint Handling can help.

Why the others are wrong:

A: energy supplier details are not listed.

B: profit is not part of a complaint record.

D: credit checks are not part of a complaint record.

Memory trick:

Log the why, not just the what.

Find it in the book

MCS Installer Operating Requirements 2.0 (2026), page 22

Reg MCS Installer Operating Requirements 2.0 (2026), Appendix A, Scenario A

Q3. Under the IOR 2.0, which of the three core roles must be filled by an employee of the company?

Show answer

Answer: C. Main Contact

  • The three core roles are Licensee, Main Contact and Technical Supervisor.
  • The Main Contact shall be an employee of the company and is the main point of contact for the Certification Body.

One person can hold all three roles in a small firm.

Why the others are wrong:

A: a Technical Supervisor can be contracted rather than employed.

B: the Licensee is defined by authority to sign, not by being an employee.

D: the assessor works for the Certification Body, not your company.

Memory trick:

Main Contact is in-house.

Find it in the book

MCS Installer Operating Requirements 2.0 (2026), page 14

Reg MCS Installer Operating Requirements 2.0 (2026), clause 5.5

Q4. A customer wants to sign only if you promise savings based on today's electricity tariff. Under the MCS Customer Commitment 1.1, what must you make them aware of?

Show answer

Answer: B. Not to sign based on specific tariffs, as they can change

  • Make the customer aware they should not sign a contract based on specific energy prices (tariffs).
  • Tariffs vary by supplier and can change, so costs can go up or down.

Performance estimates must still be realistic and truthful.

Why the others are wrong:

A: tariffs vary by supplier and can change.

C: MCS does not guarantee tariff-based savings.

D: there is no requirement to switch supplier.

Memory trick:

Tariffs move; contracts shouldn't rely on them.

Find it in the book

MCS Customer Commitment 1.1 (2026), page 6

Reg MCS Customer Commitment 1.1 (2026), section 4(j)

Q5. Fitting a heat pump will mean drilling through a roof or wall that has its own warranty, which might void it. Under the MCS Customer Commitment 1.1, what must you do?

Show answer

Answer: C. Tell the customer in writing and get written permission first

  • Let the customer know if the installation might invalidate an existing warranty.
  • You must tell them in writing and get their written permission before going ahead.

The Commitment gives a roof warranty as an example.

Why the others are wrong:

A: it must be raised before the work, not after.

B: a verbal warning on the day is not enough.

D: you must tell them in writing and get written permission before going ahead.

Memory trick:

Might void it? Write it, get it signed.

Find it in the book

MCS Customer Commitment 1.1 (2026), page 5

Reg MCS Customer Commitment 1.1 (2026), section 3(k)

Q6. A customer emails a complaint about a noisy pump. Under the MCS Customer Commitment 1.1, within what time must you acknowledge it?

Show answer

Answer: B. Two working days

  • Acknowledge a complaint within two working days and respond effectively.
  • If the customer is unhappy with the outcome, signpost the MCS complaints process.

ADR with the MCS provider follows if no resolution is reached.

Why the others are wrong:

A: fourteen days is not the acknowledgement time.

C: the Commitment sets two working days, not five.

D: 30 calendar days is for handing over documents such as the MCS certificate.

Memory trick:

Two days to say 'got it'.

Find it in the book

MCS Customer Commitment 1.1 (2026), page 7

Reg MCS Customer Commitment 1.1 (2026), section 6(c)

Want 154 more MCS Heat Pumps and BUS questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other MCS Heat Pumps and BUS topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (Ofgem, GOV.UK). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic