Q1. Under the MCS Installer Operating Requirements 2.0 (redeveloped MCS scheme), how soon after commissioning must you raise the MCS certificate?
Show answer
Answer: C. Within 30 calendar days
- Raise an MCS certificate within 30 calendar days of commissioning.
- The certificate is your declaration that the installation meets scheme requirements.
You must also record the Technical Supervisor for each installation.
Why the others are wrong:
A: 6 months is the GSHP voucher validity, not the certificate deadline.
B: 10 working days is not the MCS certificate deadline.
D: 120 days is the BUS application window after commissioning.
Memory trick:
Thirty days to certify.
Find it in the book
MCS Installer Operating Requirements 2.0 (2026), page 13