G3 Unvented: Installation, notification and commissioning practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

11 of our 60 Unvented Hot Water Storage Systems (G3) (G3-UNVENTED) questions are on installation, notification and commissioning, about 18% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. An installer is commissioning a new hot water system in an existing house. Which approved procedure does Approved Document G say should be followed?

Show answer

Answer: B. The Domestic Heating Compliance Guide

  • 3.74: commissioning must follow a procedure approved by the Secretary of State.
  • For new and existing dwellings: the Domestic Heating Compliance Guide.
  • For buildings other than dwellings: CIBSE Commissioning Code M.
  • 3.76: whoever commissions, installer, subcontractor or specialist, must follow it.

Why the others are wrong:

A: Code M is the approved procedure for buildings other than dwellings.

C: BS 8000-15 is a workmanship standard, not the approved commissioning procedure.

D: that guides the Water Fittings Regulations, not commissioning for energy use.

Memory trick:

Dwellings: Domestic guide. Non-domestic: Code M.

Reg Approved Document G, 3.74

Q2. A plumber replaces a faulty under-sink electric water heater with a new 15 litre unvented one. The electrical work involved is not notifiable. Does the water heater installation need to be notified?

Show answer

Answer: B. No, a vessel of 15 litres or less is non-notifiable

  • Schedule 4 lists as non-notifiable: providing a hot water storage system with a vessel not exceeding 15 litres, provided any associated electrical work is also not notifiable.
  • Health and safety requirements still apply; only notification is removed.
  • Where only Schedule 4 work is done, no compliance certificate is needed for the occupier or BCB.

Why the others are wrong:

A: Schedule 4 removes the need to notify for vessels not exceeding 15 litres.

C: the threshold in Schedule 4 is 15 litres, not 10.

D: the work must still comply with Part G; only the notification is removed.

Memory trick:

15 litres or less and no notifiable wiring: no notice needed.

Reg Approved Document G, General guidance: Schedule 4 item v

Q3. A building control surveyor checks the indelible marking on an indirect unvented unit. Which item must the manufacturer's marking include?

Show answer

Answer: A. The maximum primary circuit pressure and flow temperature

  • 3.23: units or packages should be indelibly marked with:
    • manufacturer's name and contact details; model reference;
    • rated storage capacity;
    • operating pressure of the system and of the expansion valve;
    • operating data for each safety device;
    • for indirect units: the maximum primary circuit pressure and flow temperature.

Why the others are wrong:

B: the marking covers the storage system, not the output of the boiler.

C: installer details go on the warning label, not the manufacturer's data.

D: room thermostat settings are not part of the required marking.

Memory trick:

Indirect units carry their primary limits on the label.

Reg Approved Document G, 3.23

Q4. A homeowner's builder fits an unvented system under a building notice with the local authority. Commissioning is finished on a Monday. By when must the notice of commissioning reach the building control body?

Show answer

Answer: C. Within 5 days of completing commissioning

  • 3.77: the person doing the work must give the BCB notice that commissioning was done to an approved procedure.
  • 3.78: under a building notice, full plans, initial notice or amendment notice: not more than 5 days after commissioning is completed.
  • In other cases, e.g. competent person scheme work: not more than 30 days after completion of the work.

Why the others are wrong:

A: the notice confirms commissioning has been done, so it follows the work.

B: 30 days applies to other cases, such as work by a registered competent person.

D: there is no 8 week period; building notice work has a much shorter deadline.

Memory trick:

Building control route: 5 days. Competent person route: 30 days.

Reg Approved Document G, 3.78

Q5. Why does Approved Document G require fixed building services such as a new hot water system and its controls to be commissioned?

Show answer

Answer: D. So they use no more fuel and power than is reasonable

  • 3.70: water heaters need energy input, so efficiency must be ensured by proper installation and commissioning.
  • 3.71: fixed building services, including controls, should be commissioned by testing and adjusting so they use no more fuel and power than is reasonable.
  • 3.72: commissioning takes the system from static completion to working order, including setting-to-work, regulation, control calibration and recording results.

Why the others are wrong:

A: warranty registration is not mentioned as the purpose of commissioning.

B: wholesomeness depends on the cold supply and the Water Fittings Regulations, not commissioning.

C: that is a scalding control under G3(4), not the purpose of commissioning.

Memory trick:

Commissioning is about efficiency: test, adjust, record.

Reg Approved Document G, 3.70 and 3.71

Q6. After fitting an unvented package, which details must the installer fill in on the warning label marked on the unit?

Show answer

Answer: A. Their name, address, phone number and the completion date

  • 3.24: the label includes a WARNING TO INSTALLER: the installation is subject to the Building Regulations; use only appropriate components for installation or maintenance.
  • Then 'Installed by': name, address, telephone number and completion date.
  • The label must be visible after installation.

Why the others are wrong:

B: that is part of the manufacturer's indelible marking under 3.23, not the installer's details.

C: the label calls for name, address, telephone and completion date only.

D: the label does not call for a service date.

Memory trick:

Who, where, phone and when: the installer's line on the label.

Reg Approved Document G, 3.24