Q1. A re-roofing project will last 40 working days with up to 25 workers on site at once. Who must notify HSE, and how?
Show answer
Answer: C. The client, using the F10 notification form
- A project must be notified if it lasts longer than 30 working days with more than 20 workers at any time, or exceeds 500 person-days.
- The client completes the F10 form on the HSE website.
This job is over 30 working days and has more than 20 workers at once, so it is notifiable.
Why the others are wrong:
A: the client, not the contractor, is responsible for completing the F10.
B: RIDDOR covers injury reporting, not project notification; the client sends the F10.
D: notification depends on duration and workforce size, not on whether it is new build.
Memory trick:
Over 30 days and over 20 people: the client sends the F10.