CITB Supervisory: Planning work, risk assessments and method statements practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

40 of our 200 CITB HS&E Specialist Test: Supervisory (CITB-SPEC-SUP) questions are on planning work, risk assessments and method statements, about 20% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. A worker asks whether your risk assessment should have covered a freak event nobody could have foreseen. What does HSG65 say?

Show answer

Answer: C. You need not anticipate unforeseeable risks

  • A risk assessment should only include what you could reasonably be expected to know.
  • You are not expected to anticipate unforeseeable risks.

After an incident, review it so the risk is now known.

Why the others are wrong:

A: HSG65 says you are not expected to anticipate the unforeseeable.

B: the client does not take over the employer's assessment.

D: the dutyholder decides, using what it could reasonably know.

Memory trick:

Reasonably foreseeable, not crystal ball.

Find it in the book

HSE HSG65 (3rd edition, 2013), page 27

Reg HSG65, 'What the law says on assessing risks'

Q2. When deciding what action to take on a risk, what should you ask first?

Show answer

Answer: B. Can the hazard be removed completely?

  • First: can the hazard be removed completely, eg a different method or material?
  • Then: can it be controlled, can measures protect the whole workforce, and can the number of people at risk be reduced?

PPE is the last resort.

Why the others are wrong:

A: reducing numbers comes after removal and control.

C: informing others is not the first control question.

D: PPE comes after removing or controlling the hazard.

Memory trick:

Remove it before you protect from it.

Find it in the book

HSE HSG150 (3rd edition, 2006), page 112

Reg HSG150 para 588, step 3 evaluate the risks

Q3. What does a method statement describe?

Show answer

Answer: A. How the job is done safely, step by step

  • A method statement describes in a logical sequence exactly how a job is to be carried out safely.
  • It includes all the control measures, so the job can be planned and resourced.

It also tells other contractors how the work will affect them.

Why the others are wrong:

B: contract terms are separate commercial documents.

C: costs are not the purpose of a method statement.

D: it plans future work, it does not assign blame.

Memory trick:

Method statement: the safe running order.

Find it in the book

HSE HSG150 (3rd edition, 2006), page 113

Reg HSG150 para 594

Q4. As a minimum, how often should you check whether a noise risk assessment needs reviewing?

Show answer

Answer: D. About every two years

  • Review the assessment if circumstances change or it is no longer valid.
  • Don't leave it for more than about two years without checking whether a review is needed.

The findings and actions must be recorded.

Why the others are wrong:

A: this is more often than the leaflet asks.

B: the leaflet says not to leave it more than about two years.

C: it should be checked regularly and when things change.

Memory trick:

Noise assessment: check every two.

Find it in the book

HSE INDG362 (rev2, 2012), page 3

Reg Control of Noise at Work Regulations 2005 (HSE INDG362), risk assessment

Q5. How should the safe system of work for a confined space entry be set out?

Show answer

Answer: B. In writing, with the work and precautions

  • To be effective, a safe system of work should be in writing, setting out the work to be done and the precautions to be taken.
  • It records that hazards were considered in advance.

It is only as good as its implementation.

Why the others are wrong:

A: precautions must be in place before work begins.

C: to be effective it should be in writing.

D: the system must be planned in advance.

Memory trick:

Confined space: write the system down.

Find it in the book

HSE L101 (3rd edition, 2014), page 24

Reg Confined Spaces Regulations 1997, regulation 4(2), L101 para 80

Q6. Which factors should a manual handling risk assessment consider?

Show answer

Answer: C. The task, load, environment and person

  • Consider risks from the task, the load, the working environment and individual capacity.
  • Also handling aids, work organisation and the pace, frequency and duration of the work.

Involve the workforce in the assessment.

Why the others are wrong:

A: the weight is just one factor.

B: timing is not the main factor.

D: individual capacity is wider than age.

Memory trick:

TILE: task, individual, load, environment.

Find it in the book

HSE INDG143 (rev4, 2020), page 5

Reg Manual Handling Operations Regulations 1992 (HSE INDG143), assess the risks

Want 194 more CITB Supervisory questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other CITB Supervisory topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (HSE). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic