Q1. On a project with several contractors, what should each contractor share from its own monitoring?
Show answer
Answer: C. Relevant findings, for project-wide checks
- Contractors should give the principal contractor any relevant information from their own monitoring.
- This lets the PC monitor health and safety at a project-wide level.
It is part of the duty to co-operate.
Why the others are wrong:
A: contractors should pass on relevant information.
B: the information goes to the principal contractor as part of co-operation.
D: costs are not the information needed.
Memory trick:
Share what you find.
Find it in the book
HSE L153 (CDM 2015), page 46