Q1. What is the minimum height of the main guard rail above the edge of a working platform?

Show answer

Answer: A. 950 mm

  • The main guard rail must be at least 950 mm above any edge from which people are liable to fall.
  • Add intermediate rails so no gap exceeds 470 mm, and a toe board.

These figures apply to scaffolds and temporary edge protection on roofs alike.

Why the others are wrong:

B: 150 mm is the minimum toe board height in HSG33.

C: this is below the minimum main guard rail height.

D: 470 mm is the largest unprotected gap allowed between rails.

Memory trick:

Nine-fifty at the top.

Find it in the book

HSE HSG150 (3rd edition, 2006), page 29

Reg HSE HSG150 (2006), para 149; HSG33, para 126

Q2. A risk assessment shows personal fall protection is needed in a boom-type MEWP. What does HSG150 say is most suitable?

Show answer

Answer: D. A short restraint lanyard to an anchor in the basket

  • A harness with a short work-restraint lanyard is the most suitable: it stops the wearer getting into a position to fall from the carrier.
  • It must be fixed to a suitable anchor point inside the basket.

It does not protect against the MEWP itself overturning.

Why the others are wrong:

A: the anchor must be a suitable point inside the basket.

B: restraint is preferred because it stops you getting into a fall position.

C: the stem says a residual risk remains, so protection is needed.

Memory trick:

Short lead, clipped inside.

Find it in the book

HSE HSG150 (3rd edition, 2006), page 35

Reg HSE HSG150 (2006), para 177

Q3. A tower scaffold in a public area will be left unattended overnight. What should be done about its access ladders?

Show answer

Answer: D. Remove or board them over

  • In public places: erect barriers at ground level and minimise materials stored on the platform.
  • Remove or board over access ladders to prevent unauthorised access if left unattended.

Children are drawn to towers and scaffolds.

Why the others are wrong:

A: a sign won't stop someone climbing up.

B: locked castors don't stop people climbing it.

C: the guidance is to stop access by removing or boarding ladders.

Memory trick:

Leaving it? Lock out the ladder.

Find it in the book

HSE HSG150 (3rd edition, 2006), page 32

Reg HSE HSG150 (2006), para 165

Q4. What is the largest unprotected gap allowed between the guard rails on a working platform?

Show answer

Answer: B. 470 mm

  • Fit enough intermediate guard rails (or suitable alternatives) so the unprotected gap does not exceed 470 mm.
  • The main guard rail is at least 950 mm high.

The intermediate rail stops people slipping under the top rail.

Why the others are wrong:

A: 950 mm is the minimum height of the main guard rail.

C: 600 mm is a typical minimum platform width, not the rail gap.

D: this is smaller than needed; the limit is 470 mm.

Memory trick:

No gap over four-seventy.

Find it in the book

HSE HSG150 (3rd edition, 2006), page 29

Reg HSE HSG150 (2006), para 149; HSG33, para 126

Q5. A MEWP operator wants to climb out of the basket at height to reach the work. What does HSG33 say?

Show answer

Answer: D. Only if a rigorous risk assessment says it is safest

  • MEWPs are designed to lift people to a position where they work from the platform.
  • Exiting the basket at height should be strictly controlled: only where a rigorous risk assessment, done when planning the job, shows it is the safest and most effective way to reach that spot.

If the work is out of reach, reposition the machine rather than climbing out.

Why the others are wrong:

A: the length of the job does not decide it; only a rigorous risk assessment can justify leaving the basket.

B: a harness alone does not make leaving the basket acceptable; it must be justified by a rigorous risk assessment.

C: a level platform does not make climbing out safe; leaving the basket is strictly controlled.

Memory trick:

Stay in the basket unless the plan proves otherwise.

Find it in the book

HSE HSG33 (5th edition, 2020), page 13

Reg HSE HSG33 (2020), para 40; HSG150, para 173

Q6. After a 7-day inspection of a scaffold over 2 m, when must the competent person give a copy of the report to the person it was done for?

Show answer

Answer: D. Within 24 hours

  • For platforms 2 m or above, after an assembly or 7-day inspection the competent person must:
  • complete the report before the end of the working period, and
  • give a copy within 24 hours to the person it was carried out for.

The report records any risks found and the action taken.

Why the others are wrong:

A: this is longer than allowed.

B: 7 days is the inspection interval, not the deadline for the report.

C: the copy is due within 24 hours.

Memory trick:

Report today, copy within a day.

Find it in the book

HSE HSG150 (3rd edition, 2006), page 27

Reg HSE HSG150 (2006), para 136

Want 114 more Working at Height questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other Working at Height topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (HSE). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic