CITB HS&E Managers: Legal and management practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

72 of our 300 CITB Health, Safety and Environment Test: Managers and Professionals (CITB-HSE-MAP) questions are on legal and management, about 24% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. Under regulation 4(4), who must the client give pre-construction information to?

Show answer

Answer: A. Every designer and contractor appointed or bidding for the work

  • The client must provide pre-construction information as soon as is practicable.
  • It goes to every designer and contractor appointed, or being considered for appointment.

The principal designer helps the client pull it together.

Why the others are wrong:

B: pre-construction information is for the project team; it is not sent to HSE with the F10.

C: it goes to every designer and contractor, including those bidding.

D: it must be provided as soon as practicable to designers and contractors.

Memory trick:

Bidding or appointed, everyone gets the info.

Find it in the book

HSE L153 (CDM 2015), page 14

Reg CDM 2015, regulation 4(4) (HSE L153)

Q2. A notifiable construction project is on a GB nuclear site. Who must the client notify instead of HSE?

Show answer

Answer: D. The Office for Nuclear Regulation

  • For work on a GB nuclear site, an authorised defence site or a new nuclear build site, the client notifies the Office for Nuclear Regulation.
  • For certain railway work it is the Office of Rail Regulation.

Otherwise the notice goes to HSE.

Why the others are wrong:

A: ORR is notified for certain railway work, not nuclear sites.

B: local authorities are not the notification body for nuclear sites.

C: the EA is not the notification body under CDM 2015.

Memory trick:

Nuclear site? Tell ONR.

Find it in the book

HSE L153 (CDM 2015), page 20

Reg CDM 2015, regulation 6(5) (HSE L153)

Q3. A bricklayer falls from a trestle. Which of these injuries is a specified injury that must be reported under RIDDOR 2013?

Show answer

Answer: B. A broken wrist

  • Specified injuries include a fracture, other than to fingers, thumbs and toes.
  • A broken wrist is therefore reportable as a specified injury.

Other specified injuries include amputations, serious burns and loss of consciousness from head injury.

Why the others are wrong:

A: a sprain is not a specified injury, and with no absence it is not reportable at all.

C: fractures to toes are excluded from the specified injuries.

D: fractures to fingers, thumbs and toes are excluded from the specified injuries.

Memory trick:

Broken bone? Report it, unless it's a finger, thumb or toe.

Find it in the book

HSE INDG453, page 2

Reg HSE INDG453, Specified injuries to workers (RIDDOR 2013, regulation 4)

Q4. HSG65 says you may need to go round the Plan, Do, Check, Act cycle more than once. In which situation is this particularly likely?

Show answer

Answer: B. When implementing any change

  • PDCA is not a once-and-for-all action.
  • You may need to go round it more than once when starting out, developing a new process, product or service, or implementing any change.

The cycle links planning, doing, checking and acting continuously.

Why the others are wrong:

A: inspections are not the trigger HSG65 gives.

C: HSG65 does not limit repeating the cycle to after accidents.

D: the cycle is continuous, not tied to the financial year.

Memory trick:

New or changed? Round the loop again.

Find it in the book

HSE HSG65 (3rd ed), page 9

Reg HSE HSG65, Figure 1 The Plan, Do, Check, Act cycle

Q5. A commercial client asks whether a health and safety file is needed for a small extension built entirely by one contractor. What does the L153 guidance say?

Show answer

Answer: D. A file is only required for projects involving more than one contractor

  • The health and safety file is only required for projects involving more than one contractor.
  • Where it is required, the client must ensure the principal designer prepares it.

The file holds information needed to carry out future construction work on the building safely.

Why the others are wrong:

A: being a domestic client is not the test for a health and safety file.

B: notification does not decide whether a file is needed; the number of contractors does.

C: the guidance limits the file to projects with more than one contractor.

Memory trick:

One contractor, no file; two or more, file.

Find it in the book

HSE L153 (CDM 2015), page 19

Reg HSE L153, para 45

Q6. On a project with several contractors, when must the principal contractor draw up the construction phase plan, or arrange for it to be drawn up?

Show answer

Answer: C. During the pre-construction phase, before the construction site is set up

  • The principal contractor must draw up the construction phase plan during the pre-construction phase.
  • It must be done before setting up a construction site.

The plan then has to be reviewed, updated and revised throughout the project.

Why the others are wrong:

A: there is no grace period; the plan must exist before the site is set up.

B: that describes the health and safety file, not the construction phase plan.

D: the plan's timing is not linked to any acknowledgement from HSE.

Memory trick:

Plan before the hoarding goes up.

Find it in the book

HSE L153 (CDM 2015), page 34

Reg CDM 2015, regulation 12(1) (HSE L153)

Want 294 more CITB HS&E Managers questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other CITB HS&E Managers topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (HSE). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic