CDM 2015: Welfare, notification and workers' duties practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

30 of our 120 CDM 2015 Awareness (CDM-AWARE) questions are on welfare, notification and workers' duties, about 25% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. Under the first notification test, a project is notifiable if it lasts longer than 30 working days and has more than how many workers working at the same time at any point?

Show answer

Answer: A. 20

  • Notifiable if scheduled to last longer than 30 working days AND have more than 20 workers working simultaneously at any point.
  • Or if it will exceed 500 person days.

Both parts of the first test must be met.

Why the others are wrong:

B: 30 is the number of working days, not the number of workers.

C: 50 is too high; the figure is more than 20.

D: 10 is too low; the figure is more than 20.

Memory trick:

30 days and 20 heads, or 500 person days.

Find it in the book

HSE L153 (CDM 2015), page 20

Reg CDM 2015, reg 6(1)(a) (HSE L153)

Q2. A shop refurbishment is planned to take 22 working days, with 25 people on site every day. Is it notifiable?

Show answer

Answer: D. Yes, it exceeds 500 person days

  • Test 1 fails: 22 days is not more than 30 working days.
  • Test 2: 22 x 25 = 550 person days, which exceeds 500, so it is notifiable.

A short job with a big gang can still need notifying.

Why the others are wrong:

A: the threshold is 500 person days, not 600.

B: that only fails the first test; the person-days test is separate.

C: 30 is not a worker threshold in either test.

The maths

Test 1: 22 days is not more than 30, so not met.
Test 2: 22 days x 25 people = 550 person days.
550 > 500, so the project is notifiable.

Memory trick:

Short but busy can still be notifiable.

Find it in the book

HSE L153 (CDM 2015), page 20

Reg CDM 2015, reg 6(1)(b) (HSE L153)

Q3. Under CDM 2015, when must a drinking water supply on site be clearly marked with a sign?

Show answer

Answer: B. Where it is needed for health or safety reasons

  • Schedule 2 says every supply of drinking water must be conspicuously marked by an appropriate sign where this is necessary for reasons of health or safety.
  • For example, where there are other taps nearby that are not safe to drink from.

The sign stops people drinking from the wrong supply.

Why the others are wrong:

A: the rule depends on health or safety need, not on whether the water is stored in a tank.

C: the number of workers is a notification threshold, not part of the drinking water rule.

D: where the tap is located is not the test; the test is whether a sign is needed for health or safety.

Memory trick:

Two taps, one safe? Sign the safe one.

Find it in the book

HSE L153 (CDM 2015), page 64

Reg CDM 2015, Schedule 2, para 3(2) (HSE L153)

Q4. Several workers on your site do not speak English as a first language. What does L153 say about health and safety information?

Show answer

Answer: D. Use clear English and other languages where needed

  • Information or instructions must be comprehensible: in simple, clear English and/or other languages where appropriate.
  • Use a logical order and illustrations, photos or diagrams where helpful.
  • Give it in good time, before work begins.

If a worker cannot understand it, it has not been provided.

Why the others are wrong:

A: L153 says photographs and diagrams can be very helpful.

B: L153 says other languages should be used where appropriate.

C: information must be given before work begins.

Memory trick:

If they can't read it, they haven't been told.

Find it in the book

HSE L153 (CDM 2015), page 25

Reg HSE L153, paras 70 to 71

Q5. When must suitable changing rooms be provided on a construction site?

Show answer

Answer: D. If workers wear special clothing and cannot change elsewhere

  • Changing rooms are needed if a worker has to wear special clothing for the work and cannot, for reasons of health or propriety, be expected to change elsewhere.
  • They must have seating and, where necessary, a way to dry clothing.

Lockers may also be needed for clothing and belongings.

Why the others are wrong:

A: this is a legal minimum, not something left to the client's brief.

B: worker numbers do not decide this; the clothing does.

C: the length of the job is a notification test, not the changing room test.

Memory trick:

Special kit, nowhere to change? Provide a changing room.

Find it in the book

HSE L153 (CDM 2015), page 64

Reg CDM 2015, Schedule 2, para 4(1) (HSE L153)

Q6. When working out the length of construction work for notification, which days count?

Show answer

Answer: B. Every day work is likely, including weekends

  • Every day construction work is likely to take place, including weekends and bank holidays, counts.
  • A 'working day' is any day on which construction work takes place.

Weekend working can push a job over the 30-day line.

Why the others are wrong:

A: weekends count if work is likely to take place.

C: the worker numbers are a separate part of the test.

D: the client's presence has nothing to do with it.

Memory trick:

If you work it, you count it.

Find it in the book

HSE L153 (CDM 2015), page 20

Reg HSE L153, para 47

Want 114 more CDM 2015 questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other CDM 2015 topics

Free official guides for this topic