Q1. Under the first notification test, a project is notifiable if it lasts longer than 30 working days and has more than how many workers working at the same time at any point?
Show answer
Answer: A. 20
- Notifiable if scheduled to last longer than 30 working days AND have more than 20 workers working simultaneously at any point.
- Or if it will exceed 500 person days.
Both parts of the first test must be met.
Why the others are wrong:
B: 30 is the number of working days, not the number of workers.
C: 50 is too high; the figure is more than 20.
D: 10 is too low; the figure is more than 20.
Memory trick:
30 days and 20 heads, or 500 person days.
Find it in the book
HSE L153 (CDM 2015), page 20