CDM 2015: Principal designer, principal contractor and key documents practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

30 of our 120 CDM 2015 Awareness (CDM-AWARE) questions are on principal designer, principal contractor and key documents, about 25% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. Two separate projects run at the same time on one site, each with its own principal contractor. What does L153 require?

Show answer

Answer: D. Clear control, with the two cooperating and coordinating

  • It is essential there is clarity over who is in control of any part of the site at any time.
  • Where one principal contractor cannot be in overall control, they must cooperate, coordinate and take account of shared interfaces such as traffic routes.

Shared roads and gates are where clashes happen.

Why the others are wrong:

A: L153 does not require the projects to be merged.

B: they must cooperate and take account of shared interfaces.

C: neither principal contractor automatically takes over the other.

Memory trick:

Two projects, one site: agree who controls what.

Find it in the book

HSE L153 (CDM 2015), page 37

Reg HSE L153, para 117

Q2. Which of these should normally be included in the health and safety file?

Show answer

Answer: C. As-built drawings and the location of services

  • The file can include as-built drawings, the nature, location and markings of significant services, hazardous materials, key structural principles and safe working loads.
  • It should not include pre-construction information, the construction phase plan, contracts or method statements.

It is for the next people who work on the building.

Why the others are wrong:

A: L153 says the plan should not be included in the file.

B: contractual documents do not help plan future work and are excluded.

D: method statements are listed as things to leave out.

Memory trick:

File for the future: what is there and where.

Find it in the book

HSE L153 (CDM 2015), page 81

Reg HSE L153, Appendix 4, paras 3 to 4

Q3. An architect visits the site now and then and is escorted the whole time. What level of induction does L153 suggest?

Show answer

Answer: D. Enough to know the main hazards and controls

  • Inductions should also be given to occasional and one-off visitors, proportionate to the visit.
  • Escorted visitors only need to be made aware of the main hazards and the control measures.
  • Unescorted visitors need more detail.

The escort covers the rest.

Why the others are wrong:

A: escorted visitors still need to know the main hazards.

B: escorted visitors need less detail than workers.

C: they need to be made aware of hazards and controls, not just sent rules.

Memory trick:

Escorted? Main hazards only.

Find it in the book

HSE L153 (CDM 2015), page 40

Reg HSE L153, para 134

Q4. How long should a client normally keep the health and safety file available?

Show answer

Answer: B. For the lifetime of the building

  • The client must retain the file and make it available for as long as it is relevant.
  • This is normally the lifetime of the building.
  • It can be kept electronically, on paper, on film or another durable form.

The next refurbishment might be 30 years away.

Why the others are wrong:

A: 3 months is the period for keeping excavation inspection reports after work ends.

C: the file is needed for as long as it is relevant, which is far longer.

D: future work can happen long after the defects period.

Memory trick:

The file lives as long as the building.

Find it in the book

HSE L153 (CDM 2015), page 82

Reg HSE L153, Appendix 4, para 7

Q5. How must a client appoint the principal designer and principal contractor?

Show answer

Answer: A. In writing

  • Where there is more than one contractor, the client must appoint in writing a principal designer and a principal contractor.
  • Appointments must be as soon as practicable, and before the construction phase begins.

Writing it down makes the roles clear to everyone.

Why the others are wrong:

B: a verbal appointment does not meet the requirement.

C: a site board is not an appointment.

D: notification lists them but is not how they are appointed.

Memory trick:

Principals are put in writing.

Find it in the book

HSE L153 (CDM 2015), page 15

Reg CDM 2015, reg 5(1) (HSE L153, para 94)

Q6. On a project with several contractors, who must draw up the construction phase plan?

Show answer

Answer: D. The principal contractor

  • On multi-contractor projects the principal contractor must draw up the construction phase plan, or arrange for it.
  • This must happen during the pre-construction phase, before the site is set up.

On a single-contractor job, the contractor does it instead.

Why the others are wrong:

A: contractors follow the relevant parts of one project plan.

B: the client must ensure the plan is drawn up, but does not write it.

C: the principal designer helps by providing information but does not draw up the plan.

Memory trick:

Principal contractor: plan before the site is set up.

Find it in the book

HSE L153 (CDM 2015), page 34

Reg CDM 2015, reg 12(1) (HSE L153, para 112)

Want 114 more CDM 2015 questions? Start a free timed mock.

Start a free mock

Full mock, no card needed. Full workouts on the first 5 questions.

Other CDM 2015 topics

Free official guides for this topic

Our questions are written from these documents. Download them free to revise from the source.

© Crown copyright (HSE). Unchanged copies, reproduced under the Open Government Licence v3.0. FreeMocks is not connected to or endorsed by HSE or the government.

Revise this topic