QELTK3/003: Planning, site organisation and supervision practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

51 of our 150 Overseeing and Organising the Work Environment (QELTK3-003) questions are on planning, site organisation and supervision, about 34% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. Why is the electric shock risk high on a construction site?

Show answer

Answer: D. Extraneous-conductive-parts often cannot practically be bonded

  • Shock risk is high on construction and demolition sites because:
  • the site is a temporary state;
  • cables and equipment can be damaged, and the site is not always sealed from the weather early on;
  • mobile equipment with trailing leads is used;
  • many extraneous-conductive-parts cannot practically be bonded because the construction keeps changing.

This is why Section 704 applies extra requirements.

Why the others are wrong:

A: construction sites use temporary supplies and mobile equipment with trailing leads.

B: sites are often not sealed from the weather in the early stages.

C: many trades and people are present, which adds to the risk.

Memory trick:

Temporary, damaged, mobile, unbonded: four reasons for shock risk.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 59

Reg AC 1.4 Construction site risks

Q2. What is the recommended practice for your power tools when they are not being used on site, including at the end of the day?

Show answer

Answer: A. Lock them in your vehicle and take them home at the end of the day

  • Tools should not be left unattended on site.
  • Keep them in your locked vehicle when not in use.
  • Power tools are expensive and easily carried away, so they should leave with you at the end of the working day.

Large items such as access equipment and generators must be made secure on site.

Why the others are wrong:

B: tools left unattended can be stolen or cause trips.

C: this is not secure storage and could damage the building.

D: this does not give you control over their security.

Memory trick:

If you can carry it, take it home.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 95

Reg AC 6.4 Secure storage

Q3. Which member of the building team finances the work and in effect employs the whole building team?

Show answer

Answer: C. The client

  • The client is the person or group with the actual need for the building.
  • The client is responsible for financing all the work and so effectively employs the entire building team.
  • A client could be an individual or a group such as a housing association.

Everything starts with the client's requirements.

Why the others are wrong:

A: the architect is the client's agent, employed by the client.

B: the main contractor carries out the work under contract to the client.

D: the quantity surveyor measures quantities and costs for the project.

Memory trick:

Client pays, so client employs.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 61

Reg AC 2.1 Building team: client

Q4. A network diagram has these activities: A-B 2 days; A-C 3 days; A-D 5 days; B-E 4 days; C-F 7 days; E-G 3 days; D-G and F-G are dummy activities. Activity B-E overruns by 2 days. What is the new total contract time?

Show answer

Answer: D. 11 days

  • Original critical path A-C-F-G = 10 days; path A-B-E-G = 9 days, so it has 1 day float.
  • With a 2 day overrun, A-B-E-G = 2 + 6 + 3 = 11 days.
  • This path now becomes critical and the contract takes 11 days.

An overrun bigger than the float delays the whole contract by the excess: 2 - 1 = 1 day.

Why the others are wrong:

A: B-E only had 1 day of float, so a 2 day overrun makes its path the longest.

B: this adds the 2 day overrun to the original 10 day critical path, but B-E is not on that path.

C: the contract time cannot fall when an activity overruns.

The maths

Dummy activities take 0 days.
Path A-B-E-G = 2 + 4 + 3 = 9 days
Path A-C-F-G = 3 + 7 + 0 = 10 days
Path A-D-G = 5 + 0 = 5 days
Float on A-B-E-G = 10 - 9 = 1 day
B-E overruns 2 days: A-B-E-G = 2 + 6 + 3 = 11 days
New longest path = 11 days, so contract time = 11 days

Memory trick:

Overrun minus float = the delay to the job.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 86

Reg AC 5.7 Network analysis

Q5. A planned delay will push up costs and affect the completion date. Which role, working for the subcontractor and often using Gantt charts, would discuss this with the client?

Show answer

Answer: C. Contracts manager

  • A contracts manager oversees projects for the subcontractor from start to completion.
  • They make sure work is finished on time and within budget, often using information from Gantt charts.
  • Planned or unplanned events affecting cost or completion are discussed with the client.

A contracts manager may run one scheme or several smaller ones.

Why the others are wrong:

A: a structural engineer deals with the stability of the building.

B: this council officer checks compliance with legislation, not programme costs.

D: specialist engineers advise the architect at the design stage.

Memory trick:

Contracts manager: time and money for the subcontractor.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 63

Reg AC 2.1 Building team: contracts manager

Q6. On a typical new build, who engages the electrical contractor as a subcontractor?

Show answer

Answer: A. The building contractor, as main contractor

  • The building contractor enters into a contract with the client and is usually the main contractor.
  • The main contractor may engage subcontractors for specialist services such as electrical installation, mechanical services, plastering and painting.
  • The electrical contractor is the subcontractor responsible for installing electrical equipment.

Subcontractors answer to the main contractor on site.

Why the others are wrong:

B: the inspector checks compliance and does not employ contractors.

C: the quantity surveyor measures and records quantities.

D: the inspector enforces law and does not engage trades.

Memory trick:

Main contractor hires the subbies.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 64

Reg AC 2.1 Main contractor and subcontractors