QELTK3/003: Communication, customer relations and health and safety practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

34 of our 150 Overseeing and Organising the Work Environment (QELTK3-003) questions are on communication, customer relations and health and safety, about 23% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. Electricians install trunking using drawings that have since been replaced by a later revision they were not given. What does the book say is the result?

Show answer

Answer: D. Wasted labour and materials, and friction

  • Information must be kept up to date, and changes passed on to relevant people.
  • Work driven by drawings that have been superseded wastes materials and labour.
  • This can cause friction, as can different trades needing access to the same area.

Sometimes a meeting is needed to find a way forward.

Why the others are wrong:

A: work to superseded drawings may need to be redone.

B: the outcome is waste and friction, not automatic payment.

C: this is not a consequence described.

Memory trick:

Old drawing, wasted day.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 79

Reg AC 4.1 Out-of-date information

Q2. Two trades agree verbally on site who will cut a shared chase through a wall. What should happen next?

Show answer

Answer: B. Record the agreement on paper so a written record exists

  • Agreements between trades are often made verbally, person to person.
  • It is vital that such agreements are also recorded on paper, so a written record exists.

If there is a dispute later, the written record settles it.

Why the others are wrong:

A: verbal agreements can be forgotten or disputed.

C: the client does not need to be involved in recording it.

D: this is not a proper record and may breach confidentiality.

Memory trick:

If it isn't written, it didn't happen.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 73

Reg AC 2.5 Verbal agreements

Q3. A customer reports a 'fishy' burning smell from the kettle socket-outlet in the kitchen. What is the most likely cause?

Show answer

Answer: D. Loose connections overheating the socket

  • A 'fishy' Bakelite smell suggests the socket is getting warm.
  • Loose connections cause the Bakelite to burn locally.
  • A visual inspection confirms it; the socket is replaced, conductors cut back if damaged, connections made tight and the kettle plug checked.

Tight connections prevent heat build-up.

Why the others are wrong:

A: a larger cable runs cooler, not hotter.

B: an RCD fault would not cause a localised burning smell at one socket.

C: an unloaded socket would not overheat.

Memory trick:

Fishy smell = loose and hot.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 69

Reg AC 2.4 Fault finding customer service

Q4. As well as the building specification and the BS 7671 certificates, a commissioning engineer needs a knowledge of which legislation?

Show answer

Answer: B. The EWR 1989 and the Health and Safety at Work Act 1974

  • The commissioning engineer has access to all contract documents, including building specifications and electrical installation certificates.
  • They must know the Electricity at Work Regulations and the Health and Safety at Work Act.

Why the others are wrong:

A: these cover personal data and employee rights, not safe commissioning of systems.

C: these relate to waste and pollution on site.

D: these deal with fair treatment of people, not system safety.

Memory trick:

Commissioning = proving it works safely: EWR plus HSWA.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 67

Reg Ch2 Commissioning

Q5. When passing information to another person, which of these is NOT one of the points the book says you should consider?

Show answer

Answer: A. Use plenty of jargon to sound professional

  • Think about the person you are communicating with, so you:
  • use the correct tone;
  • give sufficient information;
  • keep it clear and not ambiguous;
  • consider their role or position;
  • use the correct format.

If you cannot give the information, refer the matter to a more senior person.

Why the others are wrong:

B: this is one of the points listed.

C: this is one of the points listed.

D: this is one of the points listed.

Memory trick:

Tone, enough, clear, who, format.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 72

Reg AC 2.5 Communicating information

Q6. A dispute between an electrician and the employer cannot be settled in-house. What does the book suggest?

Show answer

Answer: D. Mediation through a union representative

  • Where disputes cannot be settled in-house, mediation may be needed.
  • A union representative negotiates on a member's behalf, aiming to instil fair working practices.
  • Harmonious relationships lead to efficient use of resources, customer satisfaction, productivity, less waste and higher profit.

A happier workforce is a more productive one.

Why the others are wrong:

A: this does not resolve the dispute fairly.

B: the HSE enforces health and safety law, not employment disputes.

C: the client is not part of employment disputes.

Memory trick:

Stuck in-house? Bring in the union rep.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 80

Reg AC 4.5 Disputes