QELTK3/003: Legislation, contracts and documentation practice questions

Written by Acacio Oliveira, founder of FreeMocks, plumbing and heating engineer (F-Gas registered).

65 of our 150 Overseeing and Organising the Work Environment (QELTK3-003) questions are on legislation, contracts and documentation, about 43% of the bank. Try 6 below with full worked answers, then practise the rest in a timed mock.

Practice questions

Pick an answer to see why it's right, why the others are wrong, and the page in the book.

Q1. You need to let the stores manager at your own firm know, in writing, that a van will collect two cable drums on Friday. Which form of communication suits this best?

Show answer

Answer: A. A short internal memo

  • A memo is internal communication used within an organisation.
  • Memos are not normally used for customers or suppliers.

A short message between colleagues in the same firm is exactly what a memo is for.

Why the others are wrong:

B: formal letters are for external correspondence; a quick internal note does not need one.

C: that records extra work outside the contract, not internal messages.

D: that is signed when goods are received from a supplier.

Memory trick:

Memo stays in-house; letters go out.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 68

Reg Ch2 Memos

Q2. On a 1:100 layout drawing a rectangular kitchen measures 42 mm by 30 mm. What is the actual floor area of the kitchen?

Show answer

Answer: B. 12.6 m²

  • Scale each dimension first: 42 mm x 100 = 4200 mm = 4.2 m; 30 mm x 100 = 3000 mm = 3.0 m.
  • Area = 4.2 x 3.0 = 12.6 m².

Always convert each length to its actual size before multiplying for an area.

Why the others are wrong:

A: this multiplies the drawn millimetre values together without scaling to metres correctly.

C: this adds the two sides and scales the sum, which gives a length, not an area.

D: this scales each side to 42 m and 3 m, so one dimension has been converted wrongly.

The maths

Length = 42 mm x 100 = 4200 mm = 4.2 m
Width = 30 mm x 100 = 3000 mm = 3.0 m
Area = 4.2 x 3.0 = 12.6 m²

Memory trick:

Scale the sides, then multiply.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 54

Reg AC 1.2 Scale drawings

Q3. After fitting a specified type of luminaire, what should be done with a copy of its manufacturer's data sheet?

Show answer

Answer: B. Put it in the job file for the client

  • Read the manufacturer's data sheet before fitting: it gives specific assembly and fixing instructions.
  • A copy should be placed in the job file for the client to receive when the job is completed.
  • User instructions are also placed in the job file for handover.

The client inherits the paperwork needed to operate and maintain the equipment.

Why the others are wrong:

A: the data sheet is needed by the client, not the supplier.

C: the client needs it for future reference and maintenance.

D: it belongs with the installation records handed to the client.

Memory trick:

Read it, fit it, file it.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 53

Reg AC 1.2 Manufacturer's data

Q4. An electrician passes a customer's phone number and address to a friend's company without the customer's consent. Which Act is breached?

Show answer

Answer: B. Data Protection Act

  • The Data Protection Act ensures that personal information is not given out without consent.
  • Passing a customer's details on without consent is a breach.

Customer information collected on job sheets must be kept confidential.

Why the others are wrong:

A: this concerns treating everyone with fairness, dignity and respect, not personal data.

C: this sets out employees' statutory rights.

D: these cover electrical safety at work.

Memory trick:

Customer data stays with you.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 92

Reg Data Protection Act

Q5. Which set of items would a client normally inherit when an installation is handed over?

Show answer

Answer: D. Operation manual, as-fitted drawings, certificates and warranties

  • At handover the client inherits an operation manual plus technical documents such as as-fitted drawings, specification details, the electrical installation certificates required by Part 6, warranties and manufacturers' guides.

In effect you are saying: here is your installation, complete with information on the systems and equipment.

Why the others are wrong:

A: these are internal company records, not handover documents for the client.

B: these relate to pricing the job, not operating the installation.

C: these are internal working documents of the contractor.

Memory trick:

Handover pack: how to run it, where it is, proof it's safe, who guarantees it.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 67

Reg AC 2.2 Handover documents

Q6. Which item would you normally expect to record on your weekly time sheet?

Show answer

Answer: C. Any travelling expenses claimed

  • A time sheet is usually a weekly document.
  • It includes the hours worked, the name of the job and any travelling expenses claimed.
  • Office staff use it to make up wages and bill hours to jobs.

Fill it in accurately: it affects both your pay and the job's costing.

Why the others are wrong:

A: that belongs on a daywork sheet or variation order.

B: that is recorded on the delivery note.

D: that information is on a job sheet.

Memory trick:

Time sheet: hours, job, travel.

Find it in the book

Linsley, Electrical Installation Work Level 3 (EAL Edition), page 69

Reg AC 2.4 Time sheets